South Broadway Complete Streets
Overview
The City of Englewood selected HDR to design significant pedestrian and cyclist improvements on two parallel multimodal corridors, known as the couplet, consisting of South Broadway and South Sherman Streets from US-285 to Belleview Avenue.
Complete Streets is a planning approach that ensures streets work for all users, including pedestrians, bicyclists, transit riders and drivers. The primary objective of this project is to enhance safety, accessibility and attractiveness for pedestrians and transit users on South Broadway. This will be achieved by implementing ADA improvements, upgrading bus stop amenities, improving lighting and landscaping along the corridor.
As part of the city's goals to improve active transportation, South Sherman Street will be developed as a safer alternative to South Broadway for cyclists. On-street biking facilities and traffic calming features will help redirect bicycle traffic away from South Broadway, creating a more comfortable and appealing route for riders.
These efforts align with Englewood’s broader goal of encouraging walking and transit use along South Broadway, while establishing South Sherman Street as the preferred corridor for bicyclists due to its reduced traffic and slower speeds. The project also includes wayfinding enhancements to improve access to RTD transit stops, as well as nearby bike routes and trails. Collectively, these improvements aim to promote public transit use and make cycling throughout Englewood more convenient and intuitive.
This project is a collaborative effort with the Colorado Department of Transportation (CDOT) and is estimated to cost approximately $7.54M for design and construction. The city cost-share of this project is 12% ($905,000.00) of the total budget with the remaining 88% ($6,635,000.00) being federally funded.
Design Renderings
Click on the images below to enlarge.
Construction Outreach
Community engagement is a key component of this project, and limited outreach efforts will be conducted to engage with stakeholders, residents and businesses within the project area. The goal of this outreach is to involve the community in finding solutions to mitigate construction impacts.
Construction Schedule
The city has awarded the construction bid for the South Broadway Complete Streets project to Essential Contractors, Inc. Construction will begin January 12, 2026 and is expected to be completed in December 2026. Work will start along the Broadway corridor, with installation of the South Sherman Bike Corridor scheduled for September 2026.

Construction Impacts
Traffic control and partial lane closures will be in place on South Broadway between Belleview and Hampden Avenue during construction. Minor impacts and delays to traffic on South Broadway are anticipated.
Sidewalk closures may be necessary for construction along South Broadway and South Sherman Street. In the event segments of sidewalk must be closed, alternative routes will be provided to ensure pedestrian connectivity and access to businesses along South Broadway.
Crews have been surveying and preparing the South Broadway corridor for the start of construction, and traffic impacts will begin Monday, January 19.
What to Expect:
- Inside lane closures near the medians along the corridor from Belleview Avenue to Hampden
- These lane closures will move along the corridor as the median work progresses
Drivers are encouraged to allow extra time for travel or use alternate routes.
The heavy equipment being used will create construction noise. Construction hours will be limited to Monday through Friday, 7 a.m.–7 p.m. Limited night and weekend work may be needed under special circumstances. Materials, equipment and debris will need to be delivered to and removed from the construction area.
Temporary Median Removal
The medians along South Broadway have been temporarily removed to help maintain traffic flow during construction. As crews reinstall the 13 bus pads along the corridor, traffic will shift around active work zones. Removing the medians allows vehicles to move safely through these areas. The medians will be reconstructed and reinstalled later in the project.
View the Proposed Design in the Roll Plot here.
Public Transportation Detours
The following bus stops will be temporarily closed while construction work occurs at each location. Only 1 to 2 bus stops will be closed at a time. Work for the project will begin from Belleview Avenue and work north towards Hampden Avenue throughout 2026.
Impacted Bus Stops:
Click the route number to check the current status (External links)
- Belleview: Northbound: #12482
- Chenango: Northbound #12498 | Southbound #12497
- Tufts: Northbound #12606 | Southbound #12607
- Stanford: (Northbound #12594 | Southbound #12595
- Quincy: Northbound #12583 | Southbound #12584
- Oxford: Northbound #12572 | Southbound #12573
- Mansfield: Northbound #12557 | Southbound #12558
- Kenyon: Northbound #12546 | Southbound #12547
Please see RTD’s route alerts page for information regarding RTD bus stop closures and detours in this area. RTD Service Alerts(External link)
Overview
The City of Englewood selected HDR to design significant pedestrian and cyclist improvements on two parallel multimodal corridors, known as the couplet, consisting of South Broadway and South Sherman Streets from US-285 to Belleview Avenue.
Complete Streets is a planning approach that ensures streets work for all users, including pedestrians, bicyclists, transit riders and drivers. The primary objective of this project is to enhance safety, accessibility and attractiveness for pedestrians and transit users on South Broadway. This will be achieved by implementing ADA improvements, upgrading bus stop amenities, improving lighting and landscaping along the corridor.
As part of the city's goals to improve active transportation, South Sherman Street will be developed as a safer alternative to South Broadway for cyclists. On-street biking facilities and traffic calming features will help redirect bicycle traffic away from South Broadway, creating a more comfortable and appealing route for riders.
These efforts align with Englewood’s broader goal of encouraging walking and transit use along South Broadway, while establishing South Sherman Street as the preferred corridor for bicyclists due to its reduced traffic and slower speeds. The project also includes wayfinding enhancements to improve access to RTD transit stops, as well as nearby bike routes and trails. Collectively, these improvements aim to promote public transit use and make cycling throughout Englewood more convenient and intuitive.
This project is a collaborative effort with the Colorado Department of Transportation (CDOT) and is estimated to cost approximately $7.54M for design and construction. The city cost-share of this project is 12% ($905,000.00) of the total budget with the remaining 88% ($6,635,000.00) being federally funded.
Design Renderings
Click on the images below to enlarge.
Construction Outreach
Community engagement is a key component of this project, and limited outreach efforts will be conducted to engage with stakeholders, residents and businesses within the project area. The goal of this outreach is to involve the community in finding solutions to mitigate construction impacts.
Construction Schedule
The city has awarded the construction bid for the South Broadway Complete Streets project to Essential Contractors, Inc. Construction will begin January 12, 2026 and is expected to be completed in December 2026. Work will start along the Broadway corridor, with installation of the South Sherman Bike Corridor scheduled for September 2026.

Construction Impacts
Traffic control and partial lane closures will be in place on South Broadway between Belleview and Hampden Avenue during construction. Minor impacts and delays to traffic on South Broadway are anticipated.
Sidewalk closures may be necessary for construction along South Broadway and South Sherman Street. In the event segments of sidewalk must be closed, alternative routes will be provided to ensure pedestrian connectivity and access to businesses along South Broadway.
Crews have been surveying and preparing the South Broadway corridor for the start of construction, and traffic impacts will begin Monday, January 19.
What to Expect:
- Inside lane closures near the medians along the corridor from Belleview Avenue to Hampden
- These lane closures will move along the corridor as the median work progresses
Drivers are encouraged to allow extra time for travel or use alternate routes.
The heavy equipment being used will create construction noise. Construction hours will be limited to Monday through Friday, 7 a.m.–7 p.m. Limited night and weekend work may be needed under special circumstances. Materials, equipment and debris will need to be delivered to and removed from the construction area.
Temporary Median Removal
The medians along South Broadway have been temporarily removed to help maintain traffic flow during construction. As crews reinstall the 13 bus pads along the corridor, traffic will shift around active work zones. Removing the medians allows vehicles to move safely through these areas. The medians will be reconstructed and reinstalled later in the project.
View the Proposed Design in the Roll Plot here.
Public Transportation Detours
The following bus stops will be temporarily closed while construction work occurs at each location. Only 1 to 2 bus stops will be closed at a time. Work for the project will begin from Belleview Avenue and work north towards Hampden Avenue throughout 2026.
Impacted Bus Stops:
Click the route number to check the current status (External links)
- Belleview: Northbound: #12482
- Chenango: Northbound #12498 | Southbound #12497
- Tufts: Northbound #12606 | Southbound #12607
- Stanford: (Northbound #12594 | Southbound #12595
- Quincy: Northbound #12583 | Southbound #12584
- Oxford: Northbound #12572 | Southbound #12573
- Mansfield: Northbound #12557 | Southbound #12558
- Kenyon: Northbound #12546 | Southbound #12547
Please see RTD’s route alerts page for information regarding RTD bus stop closures and detours in this area. RTD Service Alerts(External link)
-
August 2026 Update
Share August 2026 Update on Facebook Share August 2026 Update on X (formerly Twitter) Share August 2026 Update on Linkedin Email August 2026 Update linkWork Performed in August
- West-side sidewalk light poles: Most locations have been completed. Approximately six light-pole locations remain on the west side of South Broadway.
- Southbound Kenyon bus stop: Work has been completed, and the bus stop has reopened.
- Oxford Avenue Improvements: Excavation and placement of base material, drainage work, concrete placement, and corner improvements.
Work Anticipated in September
Construction activities will continue throughout the South Broadway corridor during September, with a primary focus on completing work near Oxford Avenue, remaining sidewalk and lighting improvements, and median work.
- Oxford Avenue Improvements: Continue excavation and placement of base material, followed byContinue reading
Work Performed in August
- West-side sidewalk light poles: Most locations have been completed. Approximately six light-pole locations remain on the west side of South Broadway.
- Southbound Kenyon bus stop: Work has been completed, and the bus stop has reopened.
- Oxford Avenue Improvements: Excavation and placement of base material, drainage work, concrete placement, and corner improvements.
Work Anticipated in September
Construction activities will continue throughout the South Broadway corridor during September, with a primary focus on completing work near Oxford Avenue, remaining sidewalk and lighting improvements, and median work.
- Oxford Avenue Improvements: Continue excavation and placement of base material, followed by curb-and-gutter forming, drainage work, concrete placement, and corner improvements.
- Oxford Avenue Bus Pad: Complete bus-pad construction along with associated concrete, grading, and restoration.
- Sidewalk and Light-Pole Work: Continue sidewalk improvements and complete the remaining light-pole locations along the west side of South Broadway.
- Median Improvements: Continue median work and installation of median cover at Mansfield, Chenango, Quincy and Kenyon avenues.
- Caisson Work: Relocate or replace caissons near Belleview Avenue and other affected locations as necessary.
- Final Restoration: Complete grading, cleanup and restoration of disturbed areas as individual construction activities are completed.
Work at S. Broadway and E. Oxford Avenue is now in its final stage.
The construction schedule in this area was extended due to an unforeseen condition at the site and a conflict with the adjacent building foundation. The project team is carefully evaluating and addressing these conditions, while continuing to advance the work toward completion.
Work activities and sequencing are subject to change based on weather, site conditions, and construction progress.
Thank you for your patience as we work to improve the South Broadway corridor and pedestrian safety.
-
July 2026 Update
Share July 2026 Update on Facebook Share July 2026 Update on X (formerly Twitter) Share July 2026 Update on Linkedin Email July 2026 Update link
Work Performed in July
- Paving operations continued on S. Broadway.
- Concrete ADA ramps, sidewalks and curbs were installed at E. Oxford Avenue, along with metal fencing and concrete planter boxes.
- The following RTD bus stops reopened following renovation work:
- Northbound Oxford on Broadway
- Southbound Mansfield on Broadway
- Northbound Kenyon on Broadway
Work Anticipated in August
Crews will continue intersection improvements at E. Mansfield Avenue and S. Broadway and E. Oxford Avenue and S. Broadway, including:
- Installation of new bus pads
- Concrete ADA ramps, sidewalks and curbs
- Concrete planter boxes
- Irrigation systems
Work Anticipated This Summer
- Planter boxes will be completedContinue reading
Work Performed in July
- Paving operations continued on S. Broadway.
- Concrete ADA ramps, sidewalks and curbs were installed at E. Oxford Avenue, along with metal fencing and concrete planter boxes.
- The following RTD bus stops reopened following renovation work:
- Northbound Oxford on Broadway
- Southbound Mansfield on Broadway
- Northbound Kenyon on Broadway
Work Anticipated in August
Crews will continue intersection improvements at E. Mansfield Avenue and S. Broadway and E. Oxford Avenue and S. Broadway, including:
- Installation of new bus pads
- Concrete ADA ramps, sidewalks and curbs
- Concrete planter boxes
- Irrigation systems
Work Anticipated This Summer
- Planter boxes will be completed, and greenery will be planted along S. Broadway in late summer.
- Median reconstruction will continue from E. Chenango Avenue to E. Quincy Avenue, allowing crews to install the final layer of asphalt at these intersections.
Work Anticipated This Fall
- Work will begin on the south end of S. Sherman Street, starting at W. Chenango Avenue and moving north, with pavement striping and signage installation.
- In late September to early October, crews will install bike lanes in both directions along the corridor.
Thank you for your patience as we revitalize the Englewood South corridor and improve pedestrian safety.
-
Road Closures Planned on South Broadway June 26
Share Road Closures Planned on South Broadway June 26 on Facebook Share Road Closures Planned on South Broadway June 26 on X (formerly Twitter) Share Road Closures Planned on South Broadway June 26 on Linkedin Email Road Closures Planned on South Broadway June 26 linkMotorists should expect brief midday traffic impacts on South Broadway on Friday, June 26, 2026, as contractors complete final asphalt work.
Southbound Broadway between Quincy Avenue and Radcliff Avenue will be temporarily closed for approximately one hour. Once that work is complete, crews will shift to the northbound lanes, resulting in a temporary closure of northbound Broadway from Quincy Avenue toward Princeton Avenue.
Detour routes and traffic control will be in place during both closures, and a uniformed traffic officer will assist motorists through the area.
Drivers should expect minor delays, follow posted detours and use caution while traveling throughContinue readingMotorists should expect brief midday traffic impacts on South Broadway on Friday, June 26, 2026, as contractors complete final asphalt work.
Southbound Broadway between Quincy Avenue and Radcliff Avenue will be temporarily closed for approximately one hour. Once that work is complete, crews will shift to the northbound lanes, resulting in a temporary closure of northbound Broadway from Quincy Avenue toward Princeton Avenue.
Detour routes and traffic control will be in place during both closures, and a uniformed traffic officer will assist motorists through the area.
Drivers should expect minor delays, follow posted detours and use caution while traveling through the work zone. Construction schedules may change due to weather or field conditions. -
June 2026 Update
Share June 2026 Update on Facebook Share June 2026 Update on X (formerly Twitter) Share June 2026 Update on Linkedin Email June 2026 Update link
Construction continues along the South Broadway corridor as part of the South Broadway Complete Streets Project.
Work Performed in May
- Demolition of the street and sidewalks was performed on S. Broadway at E. Mansfield Avenue.
- Street and sidewalks were removed, and a new concrete curb, gutter, ADA ramps, planter boxes, bus pads, and sidewalk were installed at E. Oxford Avenue.
Work Anticipated in June
- Paving operations continued on S. Broadway.
- Removal of the street and sidewalk will take place at the corner of E. Kenyon Avenue.
- Concrete ADA ramps were poured, irrigation work was performed, and a new light pole was installed at E. Mansfield Avenue.
- The RTD Bus Stop at the following locations will still be temporarily closed to allow crews to perform renovation work.
- NB Oxford on Broadway – Will reopen on June 15
- SB Mansfield on Broadway – Expected to reopen on June 21
- NB Kenyon on Broadway – Expected to reopen July 4
Work Anticipated in the summer
- Planter boxes are built, and greenery will be planted in late summer along S. Broadway.
- Median reconstruction will begin from E. Chenango Avenue to E. Quincy Avenue. This will allow crews to install the final mat of asphalt at these intersections.
Thank you for your patience as we revitalize the Englewood South corridor and improve pedestrian safety.
Construction continues along the South Broadway corridor as part of the South Broadway Complete Streets Project.
Work Performed in May
- Demolition of the street and sidewalks was performed on S. Broadway at E. Mansfield Avenue.
- Street and sidewalks were removed, and a new concrete curb, gutter, ADA ramps, planter boxes, bus pads, and sidewalk were installed at E. Oxford Avenue.
Work Anticipated in June
- Paving operations continued on S. Broadway.
- Removal of the street and sidewalk will take place at the corner of E. Kenyon Avenue.
- Concrete ADA ramps were poured, irrigation work was performed, and a new light pole was installed at E. Mansfield Avenue.
- The RTD Bus Stop at the following locations will still be temporarily closed to allow crews to perform renovation work.
- NB Oxford on Broadway – Will reopen on June 15
- SB Mansfield on Broadway – Expected to reopen on June 21
- NB Kenyon on Broadway – Expected to reopen July 4
Work Anticipated in the summer
- Planter boxes are built, and greenery will be planted in late summer along S. Broadway.
- Median reconstruction will begin from E. Chenango Avenue to E. Quincy Avenue. This will allow crews to install the final mat of asphalt at these intersections.
Thank you for your patience as we revitalize the Englewood South corridor and improve pedestrian safety.
-
May 2026 Project Update
Share May 2026 Project Update on Facebook Share May 2026 Project Update on X (formerly Twitter) Share May 2026 Project Update on Linkedin Email May 2026 Project Update linkConstruction continues along the South Broadway corridor as part of the South Broadway Complete Streets Project.
Work Performed in April
- Demolition of street and sidewalks was performed on S. Broadway at E. Oxford and E. Quincy Avenues.
- Electrical conduits were run to light pole locations.
- New concrete curb, gutter, ADA ramps, planter boxes, bus pads and sidewalk were poured at E. Tufts and E. Quincy Avenues.
Work Anticipated in May
- Paving operations continued on S. Broadway between E. Belleview and E. Oxford Avenues.
- The RTD Bus Stop at the following locations will still be temporarily closed to allow crews to perform renovation work.
- SB Quincy on Broadway – April 21 – May 21
- NB Oxford on Broadway – April 28 – May 28
- SB Mansfield on Broadway – May 4 – June 4
- NB Kenyon on Broadway – May 11 – June 11
- Removal of the street and sidewalk will take place at the corner of E. Mansfield Avenue
- The RTD Bus Stop at Quincy and Broadway is expected to be temporarily closed to allow crews to perform renovation work.
Work Anticipated in the summer
Planter boxes are built, and greenery will be planted in late summer along S. Broadway.
Construction continues along the South Broadway corridor as part of the South Broadway Complete Streets Project.
Work Performed in April
- Demolition of street and sidewalks was performed on S. Broadway at E. Oxford and E. Quincy Avenues.
- Electrical conduits were run to light pole locations.
- New concrete curb, gutter, ADA ramps, planter boxes, bus pads and sidewalk were poured at E. Tufts and E. Quincy Avenues.
Work Anticipated in May
- Paving operations continued on S. Broadway between E. Belleview and E. Oxford Avenues.
- The RTD Bus Stop at the following locations will still be temporarily closed to allow crews to perform renovation work.
- SB Quincy on Broadway – April 21 – May 21
- NB Oxford on Broadway – April 28 – May 28
- SB Mansfield on Broadway – May 4 – June 4
- NB Kenyon on Broadway – May 11 – June 11
- Removal of the street and sidewalk will take place at the corner of E. Mansfield Avenue
- The RTD Bus Stop at Quincy and Broadway is expected to be temporarily closed to allow crews to perform renovation work.
Work Anticipated in the summer
Planter boxes are built, and greenery will be planted in late summer along S. Broadway.
-
April 2026 Project Update
Share April 2026 Project Update on Facebook Share April 2026 Project Update on X (formerly Twitter) Share April 2026 Project Update on Linkedin Email April 2026 Project Update linkConstruction continues along the South Broadway corridor as part of the South Broadway Complete Streets Project.
March Highlights
Paving operations continue on S. Broadway between E Belleview Ave. and E Quincy Avenue
Underground pipes installed at new light pole locations
Street and sidewalk demolition completed at E. Tufts Avenue and E. Quincy Avenue
New curb, gutter, ADA ramps, planter boxes and sidewalk were poured at E. Chenango Ave. and Tufts Ave.
Coming Up in April
Paving will continue on S. Broadway between E. Belleview Ave. and E. Quincy Ave.
Planter boxes will be placed along the corridor and plants will be planted soon
April closures to be aware of:
The RTD Bus Stop at E. Quincy Avenue is temporarily closed to allow crews to perform renovation work
Sidewalk and asphalt removal will take place at the southwest corner of Chenango Avenue and the southeast corner of Tufts Avenue. Both corners are expected to reopen by April 30
These improvements will bring upgraded bus stops, safer intersections and streetscape enhancements, creating a more connected and welcoming corridor for our community. Construction is expected to be complete by the end of the year.





Construction continues along the South Broadway corridor as part of the South Broadway Complete Streets Project.
March Highlights
Paving operations continue on S. Broadway between E Belleview Ave. and E Quincy Avenue
Underground pipes installed at new light pole locations
Street and sidewalk demolition completed at E. Tufts Avenue and E. Quincy Avenue
New curb, gutter, ADA ramps, planter boxes and sidewalk were poured at E. Chenango Ave. and Tufts Ave.
Coming Up in April
Paving will continue on S. Broadway between E. Belleview Ave. and E. Quincy Ave.
Planter boxes will be placed along the corridor and plants will be planted soon
April closures to be aware of:
The RTD Bus Stop at E. Quincy Avenue is temporarily closed to allow crews to perform renovation work
Sidewalk and asphalt removal will take place at the southwest corner of Chenango Avenue and the southeast corner of Tufts Avenue. Both corners are expected to reopen by April 30
These improvements will bring upgraded bus stops, safer intersections and streetscape enhancements, creating a more connected and welcoming corridor for our community. Construction is expected to be complete by the end of the year.





-
March 2026 Project Update
Share March 2026 Project Update on Facebook Share March 2026 Project Update on X (formerly Twitter) Share March 2026 Project Update on Linkedin Email March 2026 Project Update link
Construction continues to move steadily along the South Broadway corridor, with several key milestones completed in February and additional improvements underway in March.
Work completed in February
- Reconstruction was completed at South Broadway and Belleview Avenue, including rebuilding the corner to meet ADA standards.
- Medians were removed along South Broadway at Chenango, Quincy, Kenyon, Oxford and Mansfield avenues to prepare for upcoming roadway improvements.
- Electrical upgrades and irrigation sleeve installation began.
- Excavation and roadway preparation were completed in advance of paving operations between Belleview and Quincy avenues.
- Construction began on the RTD bus stop at Chenango Avenue.
- Reconstruction of the RTD bus stop at South Broadway and Belleview Avenue was completed. A bus shelter will be reinstalled at this location later in the project.
Work anticipated in March
- Paving operations will continue between Belleview and Quincy avenues.
- Installation of electrical conduits, light pole caissons and poles will take place at Chenango Avenue, with similar work planned later in March at Quincy and Tufts avenues.
- Street and sidewalk demolition will occur at Tufts and Quincy avenues.
- New concrete curb, gutter, ADA ramps, planter boxes and sidewalk will be poured at Chenango Avenue.
- From early March through mid-April, the RTD bus stop at Quincy Avenue is expected to be temporarily closed to allow renovation work
Temporary Median Removal
The medians along South Broadway have been temporarily removed to help maintain traffic flow during construction. As crews reinstall the 13 bus pads along the corridor, traffic will shift around active work zones. Removing the medians allows vehicles to move safely through these areas. The medians will be reconstructed and reinstalled later in the project.We appreciate the community’s patience as these improvements take shape and help create a safer, more accessible South Broadway for everyone.


Construction continues to move steadily along the South Broadway corridor, with several key milestones completed in February and additional improvements underway in March.
Work completed in February
- Reconstruction was completed at South Broadway and Belleview Avenue, including rebuilding the corner to meet ADA standards.
- Medians were removed along South Broadway at Chenango, Quincy, Kenyon, Oxford and Mansfield avenues to prepare for upcoming roadway improvements.
- Electrical upgrades and irrigation sleeve installation began.
- Excavation and roadway preparation were completed in advance of paving operations between Belleview and Quincy avenues.
- Construction began on the RTD bus stop at Chenango Avenue.
- Reconstruction of the RTD bus stop at South Broadway and Belleview Avenue was completed. A bus shelter will be reinstalled at this location later in the project.
Work anticipated in March
- Paving operations will continue between Belleview and Quincy avenues.
- Installation of electrical conduits, light pole caissons and poles will take place at Chenango Avenue, with similar work planned later in March at Quincy and Tufts avenues.
- Street and sidewalk demolition will occur at Tufts and Quincy avenues.
- New concrete curb, gutter, ADA ramps, planter boxes and sidewalk will be poured at Chenango Avenue.
- From early March through mid-April, the RTD bus stop at Quincy Avenue is expected to be temporarily closed to allow renovation work
Temporary Median Removal
The medians along South Broadway have been temporarily removed to help maintain traffic flow during construction. As crews reinstall the 13 bus pads along the corridor, traffic will shift around active work zones. Removing the medians allows vehicles to move safely through these areas. The medians will be reconstructed and reinstalled later in the project.We appreciate the community’s patience as these improvements take shape and help create a safer, more accessible South Broadway for everyone.


-
February 2026 Project Update
Share February 2026 Project Update on Facebook Share February 2026 Project Update on X (formerly Twitter) Share February 2026 Project Update on Linkedin Email February 2026 Project Update link
The South Broadway Complete Streets project is officially underway. Crews are making steady progress on efforts to improve safety, accessibility and transit efficiency throughout the corridor. Here’s a look at what was accomplished last month and what you can expect in the weeks ahead.
Work performed in January
Construction activities began in January with the installation of traffic control devices throughout the project limits. Initial impacts occurred at Belleview Avenue and South Broadway, including the temporary closure of the RTD bus stop. This closure allowed crews to reconstruct the corner to meet ADA standards and provide an improved bus stop.The South Broadway Complete Streets project is officially underway. Crews are making steady progress on efforts to improve safety, accessibility and transit efficiency throughout the corridor. Here’s a look at what was accomplished last month and what you can expect in the weeks ahead.
Work performed in January
Construction activities began in January with the installation of traffic control devices throughout the project limits. Initial impacts occurred at Belleview Avenue and South Broadway, including the temporary closure of the RTD bus stop. This closure allowed crews to reconstruct the corner to meet ADA standards and provide an improved bus stop.Median removal also began along the South Broadway corridor.
Work anticipated in February
Construction at the RTD bus stop and the intersection of Belleview Avenue and S. Broadway is anticipated to be completed in early February. Median removal operations will continue along the corridor.Beginning in mid-February, the RTD bus stop at Chenango Avenue is expected to be temporarily closed so crews can complete renovation work. Please see RTD’s route alerts page for information regarding RTD bus stop closures and detours in this area. RTD Service Alerts


-
January 2026 Construction Update
Share January 2026 Construction Update on Facebook Share January 2026 Construction Update on X (formerly Twitter) Share January 2026 Construction Update on Linkedin Email January 2026 Construction Update linkCrews have been surveying and preparing the South Broadway corridor for the start of construction, and traffic impacts will begin Monday, January 19.
What to Expect:
- Inside lane closures near the medians along the corridor from Belleview Avenue to Hampden
- These lane closures will move along the corridor as the median work progresses through late February
Drivers are encouraged to allow extra time for travel or use alternate routes.
The South Broadway Complete Streets project will bring upgraded bus stops and intersections, new bike infrastructure on South Sherman Street and streetscape improvements such as lighting, wayfinding and landscaping. These updates support a safer, more connected and welcoming corridor for everyone who travels through South Broadway.
Crews have been surveying and preparing the South Broadway corridor for the start of construction, and traffic impacts will begin Monday, January 19.
What to Expect:
- Inside lane closures near the medians along the corridor from Belleview Avenue to Hampden
- These lane closures will move along the corridor as the median work progresses through late February
Drivers are encouraged to allow extra time for travel or use alternate routes.
The South Broadway Complete Streets project will bring upgraded bus stops and intersections, new bike infrastructure on South Sherman Street and streetscape improvements such as lighting, wayfinding and landscaping. These updates support a safer, more connected and welcoming corridor for everyone who travels through South Broadway.
-
Exciting Updates Coming to South Broadway – Construction Begins
Share Exciting Updates Coming to South Broadway – Construction Begins on Facebook Share Exciting Updates Coming to South Broadway – Construction Begins on X (formerly Twitter) Share Exciting Updates Coming to South Broadway – Construction Begins on Linkedin Email Exciting Updates Coming to South Broadway – Construction Begins link
Contractor mobilization for the South Broadway Complete Streets project will begin Monday, January 12, near Belleview Avenue and South Broadway to perform surveying. Construction will follow shortly after, with minor turn lane and inside lane closures between Belleview and Layton avenues expected over the next two weeks.
The Northbound RTD bus stop at Belleview will be closed starting Tuesday, January 13 and is expected to reopen on January 23.
These improvements will enhance how people move through and experience South Broadway and include upgraded bus stops and intersections, new bike infrastructure on South Sherman and streetscape improvements such as lighting, wayfinding and landscaping. Together, these updates support a safer, more connected and welcoming corridor for our community.
Contractor mobilization for the South Broadway Complete Streets project will begin Monday, January 12, near Belleview Avenue and South Broadway to perform surveying. Construction will follow shortly after, with minor turn lane and inside lane closures between Belleview and Layton avenues expected over the next two weeks.
The Northbound RTD bus stop at Belleview will be closed starting Tuesday, January 13 and is expected to reopen on January 23.
These improvements will enhance how people move through and experience South Broadway and include upgraded bus stops and intersections, new bike infrastructure on South Sherman and streetscape improvements such as lighting, wayfinding and landscaping. Together, these updates support a safer, more connected and welcoming corridor for our community.
-
Project Hotline
Phone 720-663-1146 Email corridorcompletestreets@gmail.com -
Phone 303-783-6855 Email mroman@englewoodco.gov -
Business Contact
EDPhone 303-762-2342 Email ecodev@englewoodco.gov
-
Executed IGA with CDOT
South Broadway Complete Streets has finished this stageApril 2023
-
Awarded Design Contract to HDR
South Broadway Complete Streets has finished this stageDecember 2023
-
30% Design
South Broadway Complete Streets has finished this stageMarch 2024
-
Open House and Public Comment
South Broadway Complete Streets has finished this stageApril 24, 2024
-
90% Design
South Broadway Complete Streets has finished this stageDecember 2024
-
100% Design
South Broadway Complete Streets has finished this stageMarch 2025
-
South Broadway Construction Begins
South Broadway Complete Streets is currently at this stageJanuary 2026
-
South Sherman Bike Corridor Installation
this is an upcoming stage for South Broadway Complete StreetsSeptember - October 2026
-
Construction Completion
this is an upcoming stage for South Broadway Complete StreetsDecember 2026
The South Broadway Revitalization Project invites community input to help shape a more vibrant, inclusive, and connected corridor.
Learn more and get involved here.
This project is part of Safety on the Move, Englewood’s Vision Zero initiative to reduce traffic fatalities and serious injuries through safer street design, enforcement and community engagement. Learn more about the program and its approach to transportation safety at englewoodco.gov/safetyonthemove.









