Work Performed in July
- Paving operations continued on S. Broadway.
- Concrete ADA ramps, sidewalks and curbs were installed at E. Oxford Avenue, along with metal fencing and concrete planter boxes.
- The following RTD bus stops reopened following renovation work:
- Northbound Oxford on Broadway
- Southbound Mansfield on Broadway
- Northbound Kenyon on Broadway
Work Anticipated in August
Crews will continue intersection improvements at E. Mansfield Avenue and S. Broadway and E. Oxford Avenue and S. Broadway, including:
- Installation of new bus pads
- Concrete ADA ramps, sidewalks and curbs
- Concrete planter boxes
- Irrigation systems
Work Anticipated This Summer
- Planter boxes will be completed, and greenery will be planted along S. Broadway in late summer.
- Median reconstruction will continue from E. Chenango Avenue to E. Quincy Avenue, allowing crews to install the final layer of asphalt at these intersections.
Work Anticipated This Fall
- Work will begin on the south end of S. Sherman Street, starting at W. Chenango Avenue and moving north, with pavement striping and signage installation.
- In late September to early October, crews will install bike lanes in both directions along the corridor.
Thank you for your patience as we revitalize the Englewood South corridor and improve pedestrian safety.
Share July 2026 Update on Facebook
Share July 2026 Update on X (formerly Twitter)
Share July 2026 Update on Linkedin
Email July 2026 Update link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends