June 2026 Update

Construction continues along the South Broadway corridor as part of the South Broadway Complete Streets Project.
Work Performed in May
- Demolition of the street and sidewalks was performed on S. Broadway at E. Mansfield Avenue.
- Street and sidewalks were removed, and a new concrete curb, gutter, ADA ramps, planter boxes, bus pads, and sidewalk were installed at E. Oxford Avenue.
Work Anticipated in June
- Paving operations continued on S. Broadway.
- Removal of the street and sidewalk will take place at the corner of E. Kenyon Avenue.
- Concrete ADA ramps were poured, irrigation work was performed, and a new light pole was installed at E. Mansfield Avenue.
- The RTD Bus Stop at the following locations will still be temporarily closed to allow crews to perform renovation work.
- NB Oxford on Broadway – Will reopen on June 15
- SB Mansfield on Broadway – Expected to reopen on June 21
- NB Kenyon on Broadway – Expected to reopen July 4
Work Anticipated in the summer
- Planter boxes are built, and greenery will be planted in late summer along S. Broadway.
- Median reconstruction will begin from E. Chenango Avenue to E. Quincy Avenue. This will allow crews to install the final mat of asphalt at these intersections.
Thank you for your patience as we revitalize the Englewood South corridor and improve pedestrian safety.
Share June 2026 Update on Facebook
Share June 2026 Update on Twitter
Share June 2026 Update on Linkedin
Email June 2026 Update link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends