This email is the twelfth in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.
In the last month, the consultant performed additional coordination with private utility companies, which was necessary to facilitate the proposed drainage and lighting infrastructure.
In the coming month, the city anticipates receiving CDOT and FHWA approval to advertise for construction. This approval allows the city to solicit bids and enter into a contract with the lowest responsible bidder.
Best,
Englewood Public Works -
12.3.21 Project Update
Share 12.3.21 Project Update on Facebook Share 12.3.21 Project Update on Twitter Share 12.3.21 Project Update on Linkedin Email 12.3.21 Project Update linkHey Englewood,This is the tenth in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.In the last month, the consultant continued to address comments on the plans & specifications from both the city and CDOT.In the coming month, the city and CDOT will confirm all necessary changes were made to the plans, specifications, and cost estimate. CDOT will seek FHWA approval for the project to be advertised for construction. Finally, the city will advertise the project for construction in late December or early January.Best,Englewood Public Works -
11.3.21 Project Update
Share 11.3.21 Project Update on Facebook Share 11.3.21 Project Update on Twitter Share 11.3.21 Project Update on Linkedin Email 11.3.21 Project Update linkHey Englewood,
This email is the ninth in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.
In the last month, the city and CDOT reviewed the plans, specifications, and cost estimate provided by the consultant. The consultant has worked to implement all comments and compile the final submittal for construction advertisement.
In the coming month, the city and CDOT will confirm all necessary changes were made to the plans, specifications, and cost estimate. CDOT will seek FHWA approval for the project to go to construction.
Best,
Englewood Public Works
-
10.1.2021 Project Update
Share 10.1.2021 Project Update on Facebook Share 10.1.2021 Project Update on Twitter Share 10.1.2021 Project Update on Linkedin Email 10.1.2021 Project Update linkHey Englewood,
This email is the eighth in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.
In the last month the project team submitted the plans and specifications package for a final review by the city and CDOT. The project team also continued the process of acquiring the necessary right-of-way for the project.
In the coming month, the city and CDOT will review the plans and specifications in order to provide feedback to the design team. The design team will incorporate comments into the design and will prepare the final plans and specifications package for bidding. Lastly, the team will continue the right-of-way acquisition process.
Best,
Englewood Public Works
-
9.2.2021 Project Update
Share 9.2.2021 Project Update on Facebook Share 9.2.2021 Project Update on Twitter Share 9.2.2021 Project Update on Linkedin Email 9.2.2021 Project Update linkHey Englewood,
This email is the seventh in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.
In the last month the project team began the process of acquiring right of way for the project and continued refining the plans and specifications. Also, staff met with City Council on August 23rd to update Council on the design progress and get direction on aesthetic treatments for the project.
In the coming month, the project team will continue the process of acquiring the necessary right of way to build the bridge. Also, the team will be submitting the 90% plans & specifications package for the City and CDOT to review.
Best,
Englewood Public Works
-
8.2.21 Project Update
Share 8.2.21 Project Update on Facebook Share 8.2.21 Project Update on Twitter Share 8.2.21 Project Update on Linkedin Email 8.2.21 Project Update linkHey Englewood,
This is the sixth update in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.
In the last month, the project team continued refining the plans and specifications as a whole. The team also developed a few aesthetic design options for review by staff and city council.
Best,
Englewood Public Works -
7.2.21 Project Update
Share 7.2.21 Project Update on Facebook Share 7.2.21 Project Update on Twitter Share 7.2.21 Project Update on Linkedin Email 7.2.21 Project Update linkHey Englewood,
This email is the fifth in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.
In the last month, the project team continued addressing comments from the City’s and CDOT’s preliminary plan review, while also continuing to refine the plans and specifications as a whole.
Best,
Englewood Public WorksPreliminary Design; may not reflect Final Design
-
6.2.21 Project Update
Share 6.2.21 Project Update on Facebook Share 6.2.21 Project Update on Twitter Share 6.2.21 Project Update on Linkedin Email 6.2.21 Project Update linkIn the last month the project team went through CDOT’s preliminary plan review process and began working through comments from both the City and CDOT. The team also developed a drainage report for the proposed design and refined the project’s right-of-way plans.
As always, please feel free to reach out to the City’s Project Manager, Jake Warren at jwarren@englewoodco.gov.
-
5.5.21 Project Update
Share 5.5.21 Project Update on Facebook Share 5.5.21 Project Update on Twitter Share 5.5.21 Project Update on Linkedin Email 5.5.21 Project Update linkThis is the third in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.In the last month, the project team finalized the structure selection report and determined the preferred structure type and configuration for the bridge. The team refined the plan and profile for the approach paths, determined where structural and landscaping retaining walls would be required, and developed preliminary plans & specifications for review by the City and CDOT.The City hosted a virtual public information meeting for the project on April 22, 2021. A recording of this meeting can be found on the project webpage: https://www.engaged.englewoodco.gov/oxford-aveBest,Englewood Public Works -
4.22.21 Meeting Recording
Share 4.22.21 Meeting Recording on Facebook Share 4.22.21 Meeting Recording on Twitter Share 4.22.21 Meeting Recording on Linkedin Email 4.22.21 Meeting Recording linkView the meeting recording below.