    This is the sixteenth in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.

    On April 7th the city opened contractors’ bids for the construction contract. The city received 5 bids, however, the low bid was higher than the Engineer’s Opinion of Probable Cost. City staff is working to find additional sources of funding in order to move forward with construction. The city also selected a consultant engineering team to perform construction management and oversight services on the project.

    Best,
    Englewood Public Works

  • 5.3.22 Update

    Share 5.3.22 Update on Facebook Share 5.3.22 Update on Twitter Share 5.3.22 Update on Linkedin Email 5.3.22 Update link

    This is the fifteenth in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.

    In the last month, the city opened contractors’ bids for the construction contract. The city received 5 bids, however, the low bid was higher than the Engineer’s Opinion of Probable Cost. City staff is working to find additional sources of funding in order to move forward with construction. The city also selected a consultant team to perform construction management and oversight on the project.

    Best,
    Englewood Public Works

  • 4.1.22 Update

    Share 4.1.22 Update on Facebook Share 4.1.22 Update on Twitter Share 4.1.22 Update on Linkedin Email 4.1.22 Update link

    Hey Englewood,

    This is the fourteenth in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.

    In the last month, the city advertised the project for construction. Bids from contractors are due on April 7th.

    In the next month, the city will close the advertising period and open bids. City staff will review the bids and work with the low bidder to prepare a contract for CDOT and City Council approval.

    Best,

    Englewood Public Works


  • 3.1.22 Update

    Share 3.1.22 Update on Facebook Share 3.1.22 Update on Twitter Share 3.1.22 Update on Linkedin Email 3.1.22 Update link

    Hey Englewood,

    This email is the thirteenth in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.

    In the last month, the city and consultant team awaited approval from CDOT and FHWA to advertise the project for construction. CDOT and FHWA provided concurrence to advertise on February 28th, allowing the city to move forward with the next phase of the project.

    In the next month, the city will advertise the project to construction contractors in an effort to obtain the lowest possible competitive bid.

    Best,

    Englewood Public Works

  • 2.2.22 Project Update

    Share 2.2.22 Project Update on Facebook Share 2.2.22 Project Update on Twitter Share 2.2.22 Project Update on Linkedin Email 2.2.22 Project Update link
    supporting image

    Hey Englewood,

    This email is the twelfth in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.

    In the last month, the consultant performed additional coordination with private utility companies, which was necessary to facilitate the proposed drainage and lighting infrastructure.

    In the coming month, the city anticipates receiving CDOT and FHWA approval to advertise for construction. This approval allows the city to solicit bids and enter into a contract with the lowest responsible bidder.

    Best,
    Englewood Public Works

  • 12.3.21 Project Update

    Share 12.3.21 Project Update on Facebook Share 12.3.21 Project Update on Twitter Share 12.3.21 Project Update on Linkedin Email 12.3.21 Project Update link
    Hey Englewood,

    This is the tenth in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.

    In the last month, the consultant continued to address comments on the plans & specifications from both the city and CDOT.

    In the coming month, the city and CDOT will confirm all necessary changes were made to the plans, specifications, and cost estimate. CDOT will seek FHWA approval for the project to be advertised for construction. Finally, the city will advertise the project for construction in late December or early January.

    Best,
    Englewood Public Works


  • 11.3.21 Project Update

    Share 11.3.21 Project Update on Facebook Share 11.3.21 Project Update on Twitter Share 11.3.21 Project Update on Linkedin Email 11.3.21 Project Update link

    Hey Englewood,

    This email is the ninth in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.

    In the last month, the city and CDOT reviewed the plans, specifications, and cost estimate provided by the consultant. The consultant has worked to implement all comments and compile the final submittal for construction advertisement.

    In the coming month, the city and CDOT will confirm all necessary changes were made to the plans, specifications, and cost estimate. CDOT will seek FHWA approval for the project to go to construction.

    Best,

    Englewood Public Works

  • 10.1.2021 Project Update

    Share 10.1.2021 Project Update on Facebook Share 10.1.2021 Project Update on Twitter Share 10.1.2021 Project Update on Linkedin Email 10.1.2021 Project Update link
    supporting image

    Hey Englewood,

    This email is the eighth in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.

    In the last month the project team submitted the plans and specifications package for a final review by the city and CDOT. The project team also continued the process of acquiring the necessary right-of-way for the project.

    In the coming month, the city and CDOT will review the plans and specifications in order to provide feedback to the design team. The design team will incorporate comments into the design and will prepare the final plans and specifications package for bidding. Lastly, the team will continue the right-of-way acquisition process.

    Best,

    Englewood Public Works

  • 9.2.2021 Project Update

    Share 9.2.2021 Project Update on Facebook Share 9.2.2021 Project Update on Twitter Share 9.2.2021 Project Update on Linkedin Email 9.2.2021 Project Update link
    supporting image

    Hey Englewood,

    This email is the seventh in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.

    In the last month the project team began the process of acquiring right of way for the project and continued refining the plans and specifications. Also, staff met with City Council on August 23rd to update Council on the design progress and get direction on aesthetic treatments for the project.

    In the coming month, the project team will continue the process of acquiring the necessary right of way to build the bridge. Also, the team will be submitting the 90% plans & specifications package for the City and CDOT to review.

    Best,

    Englewood Public Works

  • 8.2.21 Project Update

    Share 8.2.21 Project Update on Facebook Share 8.2.21 Project Update on Twitter Share 8.2.21 Project Update on Linkedin Email 8.2.21 Project Update link

    Hey Englewood,

    This is the sixth update in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.

    In the last month, the project team continued refining the plans and specifications as a whole. The team also developed a few aesthetic design options for review by staff and city council.

    Best,
    Englewood Public Works