Old Hampden Utility Improvements

Share Old Hampden Utility Improvements on Facebook Share Old Hampden Utility Improvements on X (formerly Twitter) Share Old Hampden Utility Improvements on Linkedin Email Old Hampden Utility Improvements link

Project Overview

Old Hampden is in need of some love, both above and below ground. This street and its aging underground water and stormwater pipelines run directly through the Wellness District of Downtown Englewood, serving Craig Hospital, Swedish Medical Center, nearby businesses and residents, office workers, and visitors with its assortment of retail stores and restaurants. Upgrading old infrastructure and enhancing public safety, accessibility and options for getting around the Old Hampden area have been key priorities for the City of Englewood and the Englewood Downtown Development Authority, as outlined through the city’s master planning process.

The Old Hampden Utility Improvements project is necessary to replace small, old 1950s-era water and stormwater pipes, manholes and infrastructure that are well past their useful life. It will prevent future water line breaks and storm-related flooding for the entire community.

Image of CCTV footage of stormwater pipe full of debris.

Aftermath of a water main break on Hampden and Washington.

The timing of each phase of the project is based on when funding is available and when contracting is finalized. To help reduce the cost of these critical infrastructure projects and limit construction-related disruptions, Englewood Utilities is working to replace the stormwater and water lines at approximately the same time.

Utility Project Phases

Phase 1: Completed January 2025 - March 2026. The first phase of stormwater system upgrades and all the water line construction was completed, with stormwater construction between South Emerson St. through S Logan St. and water line work along the entire Old Hampden Ave. corridor.

Phase 2: Scheduled from mid - August into October 2026 (six to eight weeks). Englewood Utilities is upgrading the next section of Old Hampden’s stormwater infrastructure between Grant and Lincoln streets – to the west of Swedish Medical Center. Continuation of this project is needed to reduce flooding and improve the capacity of the stormwater system. This phase of construction will be much shorter than the previous work. See below details on what to expect.

Phase 3: Planned for fall 2026, for up to three weeks. The final phase of the stormwater improvements project in this area is planned for this fall. It will temporarily close the south end of Lincoln Street adjacent to Little Dry Creek, while keeping Old Hampden partially open east-west.

Old Hampden Aug-Oct 2026 Construction: What To Expect

Construction hours: Monday through Friday, 7:00 a.m. to 4:00 p.m

Project Duration: About six to eight weeks.

Impacts:

  • Some large equipment and excavations, as well as potential noise and dust during construction hours. Crews will work to minimize impacts as much as possible.
  • No direct access to any property is expected to be cut off.
  • We are communicating directly with neighbors and businesses in the area and will provide updates online here as well.

Street Closure Info:

  • Old Hampden: Closed to traffic between Grant and Lincoln until project completion.
  • Sherman Street/Old Hampden intersection: Closed until project completion.
  • Lincoln/Hampden intersection: Closed until project completion.
  • Grant/Hampden intersection: Closed until project completion.
  • Logan/Hampden intersection: Open to north/south traffic.

Contact Information & Project Updates

For questions or concerns, please contact: Utilitiesdevreview@englewoodco.gov.

Project Overview

Old Hampden is in need of some love, both above and below ground. This street and its aging underground water and stormwater pipelines run directly through the Wellness District of Downtown Englewood, serving Craig Hospital, Swedish Medical Center, nearby businesses and residents, office workers, and visitors with its assortment of retail stores and restaurants. Upgrading old infrastructure and enhancing public safety, accessibility and options for getting around the Old Hampden area have been key priorities for the City of Englewood and the Englewood Downtown Development Authority, as outlined through the city’s master planning process.

The Old Hampden Utility Improvements project is necessary to replace small, old 1950s-era water and stormwater pipes, manholes and infrastructure that are well past their useful life. It will prevent future water line breaks and storm-related flooding for the entire community.

Image of CCTV footage of stormwater pipe full of debris.

Aftermath of a water main break on Hampden and Washington.

The timing of each phase of the project is based on when funding is available and when contracting is finalized. To help reduce the cost of these critical infrastructure projects and limit construction-related disruptions, Englewood Utilities is working to replace the stormwater and water lines at approximately the same time.

Utility Project Phases

Phase 1: Completed January 2025 - March 2026. The first phase of stormwater system upgrades and all the water line construction was completed, with stormwater construction between South Emerson St. through S Logan St. and water line work along the entire Old Hampden Ave. corridor.

Phase 2: Scheduled from mid - August into October 2026 (six to eight weeks). Englewood Utilities is upgrading the next section of Old Hampden’s stormwater infrastructure between Grant and Lincoln streets – to the west of Swedish Medical Center. Continuation of this project is needed to reduce flooding and improve the capacity of the stormwater system. This phase of construction will be much shorter than the previous work. See below details on what to expect.

Phase 3: Planned for fall 2026, for up to three weeks. The final phase of the stormwater improvements project in this area is planned for this fall. It will temporarily close the south end of Lincoln Street adjacent to Little Dry Creek, while keeping Old Hampden partially open east-west.

Old Hampden Aug-Oct 2026 Construction: What To Expect

Construction hours: Monday through Friday, 7:00 a.m. to 4:00 p.m

Project Duration: About six to eight weeks.

Impacts:

  • Some large equipment and excavations, as well as potential noise and dust during construction hours. Crews will work to minimize impacts as much as possible.
  • No direct access to any property is expected to be cut off.
  • We are communicating directly with neighbors and businesses in the area and will provide updates online here as well.

Street Closure Info:

  • Old Hampden: Closed to traffic between Grant and Lincoln until project completion.
  • Sherman Street/Old Hampden intersection: Closed until project completion.
  • Lincoln/Hampden intersection: Closed until project completion.
  • Grant/Hampden intersection: Closed until project completion.
  • Logan/Hampden intersection: Open to north/south traffic.

Contact Information & Project Updates

For questions or concerns, please contact: Utilitiesdevreview@englewoodco.gov.

  • July 2026 Update

    Share July 2026 Update on Facebook Share July 2026 Update on X (formerly Twitter) Share July 2026 Update on Linkedin Email July 2026 Update link

    For about 6-8 weeks starting in mid-August, Englewood Utilities will continue crucial stormwater system upgrades along Old Hampden Avenue, between Grant and Lincoln streets. These improvements have been planned and funded to replace small, 1950s-era pipes and prevent storm-related flooding. No direct access to any property will be cut off. Businesses and residents in this area are being notified.

    Please follow posted detour signs and keep a safe distance from work areas and equipment.

    For about 6-8 weeks starting in mid-August, Englewood Utilities will continue crucial stormwater system upgrades along Old Hampden Avenue, between Grant and Lincoln streets. These improvements have been planned and funded to replace small, 1950s-era pipes and prevent storm-related flooding. No direct access to any property will be cut off. Businesses and residents in this area are being notified.

    Please follow posted detour signs and keep a safe distance from work areas and equipment.

  • March 2026 Old Hampden Utilities Update

    Share March 2026 Old Hampden Utilities Update on Facebook Share March 2026 Old Hampden Utilities Update on X (formerly Twitter) Share March 2026 Old Hampden Utilities Update on Linkedin Email March 2026 Old Hampden Utilities Update link

    Work on waterlines along Old Hampden Avenue east of Broadway is complete. The roadway has been patched, paved and reopened to traffic.

    Next, Xcel Energy will begin moving overhead electrical lines underground between Clarkson and Lafayette avenues. This work will make the corridor look better and improve reliability.

    The utilities department is in the process of signing an additional contract to install stormwater improvements on Old Hampden from Lincoln Street to Grant Street. This work will require a full road closure between those streets and is expected to start in late April or early May.

    Later this spring or early summer, construction will begin on the Complete Streets portion of the project. This work will transform Old Hampden from a car-focused road with safety and access challenges into a safer, more welcoming space for everyone. Planned improvements include ADA upgrades, wider sidewalks, upgraded bus stops, traffic-calming features and safer crossings for drivers, bicyclists and pedestrians.

    Work on waterlines along Old Hampden Avenue east of Broadway is complete. The roadway has been patched, paved and reopened to traffic.

    Next, Xcel Energy will begin moving overhead electrical lines underground between Clarkson and Lafayette avenues. This work will make the corridor look better and improve reliability.

    The utilities department is in the process of signing an additional contract to install stormwater improvements on Old Hampden from Lincoln Street to Grant Street. This work will require a full road closure between those streets and is expected to start in late April or early May.

    Later this spring or early summer, construction will begin on the Complete Streets portion of the project. This work will transform Old Hampden from a car-focused road with safety and access challenges into a safer, more welcoming space for everyone. Planned improvements include ADA upgrades, wider sidewalks, upgraded bus stops, traffic-calming features and safer crossings for drivers, bicyclists and pedestrians.

  • January/February 2026 Project Update

    Share January/February 2026 Project Update on Facebook Share January/February 2026 Project Update on X (formerly Twitter) Share January/February 2026 Project Update on Linkedin Email January/February 2026 Project Update link
    supporting image

    Work is continuing on Old Hampden Avenue between Broadway and Sherman streets as crews install new water mains. Turns onto Hampden from Broadway are currently prohibited in all directions. The street is expected to reopen in late February 2026.

    This work is part of a larger effort to upgrade aging utility infrastructure along the corridor. Water and stormwater pipes installed in the 1950s are nearing the end of their useful life and have contributed to water main breaks and storm-related flooding in the area. These improvements will help ensure more reliable water service and better stormwater management for the community.

    Work is continuing on Old Hampden Avenue between Broadway and Sherman streets as crews install new water mains. Turns onto Hampden from Broadway are currently prohibited in all directions. The street is expected to reopen in late February 2026.

    This work is part of a larger effort to upgrade aging utility infrastructure along the corridor. Water and stormwater pipes installed in the 1950s are nearing the end of their useful life and have contributed to water main breaks and storm-related flooding in the area. These improvements will help ensure more reliable water service and better stormwater management for the community.

  • December 2025 Update

    Share December 2025 Update on Facebook Share December 2025 Update on X (formerly Twitter) Share December 2025 Update on Linkedin Email December 2025 Update link

    New traffic control changes will begin the week of December 8 as the contractor wraps up work at Old Hampden Avenue and South Clarkson Street. Once that intersection is complete, crews will move to Grant Street to install a new stormwater inlet at the Old Hampden and Grant Street intersection.

    These closures are part of the Old Hampden Utility Improvement Project, which is replacing and upgrading underground utilities to strengthen the area’s infrastructure. This work is laying the foundation for planned streetscape improvements coming in 2026, creating a safer, more reliable and more welcoming corridor for residents, businesses and visitors

    New traffic control changes will begin the week of December 8 as the contractor wraps up work at Old Hampden Avenue and South Clarkson Street. Once that intersection is complete, crews will move to Grant Street to install a new stormwater inlet at the Old Hampden and Grant Street intersection.

    These closures are part of the Old Hampden Utility Improvement Project, which is replacing and upgrading underground utilities to strengthen the area’s infrastructure. This work is laying the foundation for planned streetscape improvements coming in 2026, creating a safer, more reliable and more welcoming corridor for residents, businesses and visitors in the area.

    Please follow posted detours and signage to navigate the construction zone.

    We appreciate your patience and cooperation as we make these critical improvements that will support the future of Old Hampden.

  • Old Hampden Improvements Update - September-December

    Share Old Hampden Improvements Update - September-December on Facebook Share Old Hampden Improvements Update - September-December on X (formerly Twitter) Share Old Hampden Improvements Update - September-December on Linkedin Email Old Hampden Improvements Update - September-December link
    supporting image

    New traffic control closures will begin on Tuesday, September 23. This phase impacts Old Hampden east of South Washington Street through the South Clarkson Street intersection.

    These closures are part of the Old Hampden Utility Improvement Project, which is replacing and upgrading underground utilities to strengthen the area’s infrastructure. This work is laying the foundation for planned streetscape improvements coming in 2026, creating a safer, more reliable and more welcoming corridor for residents, businesses and visitors in the area.

    Please follow posted detours and signage to get around the construction zone.

    We appreciate your patience and cooperation as we make

    New traffic control closures will begin on Tuesday, September 23. This phase impacts Old Hampden east of South Washington Street through the South Clarkson Street intersection.

    These closures are part of the Old Hampden Utility Improvement Project, which is replacing and upgrading underground utilities to strengthen the area’s infrastructure. This work is laying the foundation for planned streetscape improvements coming in 2026, creating a safer, more reliable and more welcoming corridor for residents, businesses and visitors in the area.

    Please follow posted detours and signage to get around the construction zone.

    We appreciate your patience and cooperation as we make these critical improvements that will support the future of Old Hampden.


  • Old Hampden Utility Improvements Update- August

    Share Old Hampden Utility Improvements Update- August on Facebook Share Old Hampden Utility Improvements Update- August on X (formerly Twitter) Share Old Hampden Utility Improvements Update- August on Linkedin Email Old Hampden Utility Improvements Update- August link
    supporting image

    The next phase Old Hampden Utility Improvement Project will begin on Wednesday, August 27, 2025. This phase impacts the area from 601 to 701 E Hampden and includes the following changes:

    • 601 E Hampden entrance – Closed to all traffic.
    • 701 E Hampden entrance – Open for deliveries and trash collection only.
    • Valet services:
      • 601 E Hampden – Valet will operate from the front of the main hospital building.
      • 701 E Hampden – Valet will move to the rear of the building.
    • Please follow posted detour routes and signage for hospital access.

    The anticipated duration for this traffic control configuration

    The next phase Old Hampden Utility Improvement Project will begin on Wednesday, August 27, 2025. This phase impacts the area from 601 to 701 E Hampden and includes the following changes:

    • 601 E Hampden entrance – Closed to all traffic.
    • 701 E Hampden entrance – Open for deliveries and trash collection only.
    • Valet services:
      • 601 E Hampden – Valet will operate from the front of the main hospital building.
      • 701 E Hampden – Valet will move to the rear of the building.
    • Please follow posted detour routes and signage for hospital access.

    The anticipated duration for this traffic control configuration is 6 to 8 weeks.

    We appreciate your patience and cooperation as we complete these critical utility improvements.

  • Old Hampden Improvements Utility Project Update

    Share Old Hampden Improvements Utility Project Update on Facebook Share Old Hampden Improvements Utility Project Update on X (formerly Twitter) Share Old Hampden Improvements Utility Project Update on Linkedin Email Old Hampden Improvements Utility Project Update link

    Construction continues in the Phase 3 closure area from Pearl Street to Washington Street. During this time:

    • Access to 601 Hampden and the hospitals is being maintained via the drive lane from the east and Pennsylvania Street from the west.

    • Crews are actively working on the redundant water feed to the hospital to enhance system reliability.

    • Work in this area is expected to continue through late August 2025.

    • Additionally, Bid Schedule D work has been added to the contract, expanding the scope of the current project.

    Thank you for your continued patience as we make these critical infrastructure improvements.

    Construction continues in the Phase 3 closure area from Pearl Street to Washington Street. During this time:

    • Access to 601 Hampden and the hospitals is being maintained via the drive lane from the east and Pennsylvania Street from the west.

    • Crews are actively working on the redundant water feed to the hospital to enhance system reliability.

    • Work in this area is expected to continue through late August 2025.

    • Additionally, Bid Schedule D work has been added to the contract, expanding the scope of the current project.

    Thank you for your continued patience as we make these critical infrastructure improvements.

  • Old Hampden Utility Improvements - July Update

    Share Old Hampden Utility Improvements - July Update on Facebook Share Old Hampden Utility Improvements - July Update on X (formerly Twitter) Share Old Hampden Utility Improvements - July Update on Linkedin Email Old Hampden Utility Improvements - July Update link

    Work is progressing on the Old Hampden Utility Improvements Project, and the next construction phase is scheduled to begin Tuesday, July 15.

    The current closure from South Logan Street to South Pearl Street will reopen to traffic, and the closure will shift east, closing Old Hampden Avenue from South Pearl Street to South Washington Street.

    Crews will continue upgrading aging utility infrastructure along the corridor, including water and stormwater pipes originally installed in the 1950s. These systems are nearing the end of their useful life and have contributed to water main breaks and storm-related flooding

    Work is progressing on the Old Hampden Utility Improvements Project, and the next construction phase is scheduled to begin Tuesday, July 15.

    The current closure from South Logan Street to South Pearl Street will reopen to traffic, and the closure will shift east, closing Old Hampden Avenue from South Pearl Street to South Washington Street.

    Crews will continue upgrading aging utility infrastructure along the corridor, including water and stormwater pipes originally installed in the 1950s. These systems are nearing the end of their useful life and have contributed to water main breaks and storm-related flooding in the area.



  • Old Hampden Utility Improvements Timeline Extended

    Share Old Hampden Utility Improvements Timeline Extended on Facebook Share Old Hampden Utility Improvements Timeline Extended on X (formerly Twitter) Share Old Hampden Utility Improvements Timeline Extended on Linkedin Email Old Hampden Utility Improvements Timeline Extended link

    As utility work continues along Old Hampden Avenue, the City of Englewood is adjusting the construction timeline to allow for a more efficient and coordinated approach. Multiple new phases will be added to the utility portion of the project, pending city council approval. This additional work ensures that the entire length of aged and decaying storm pipe will be replaced prior to the Complete Streets construction, reducing the risk of failure of old pipe under new improvements, limiting the need to revisit completed areas and minimizing disruption to surrounding businesses, hospitals and residents.

    The Complete Streets streetscape improvements originally planned

    As utility work continues along Old Hampden Avenue, the City of Englewood is adjusting the construction timeline to allow for a more efficient and coordinated approach. Multiple new phases will be added to the utility portion of the project, pending city council approval. This additional work ensures that the entire length of aged and decaying storm pipe will be replaced prior to the Complete Streets construction, reducing the risk of failure of old pipe under new improvements, limiting the need to revisit completed areas and minimizing disruption to surrounding businesses, hospitals and residents.

    The Complete Streets streetscape improvements originally planned to begin this fall will now be postponed. The project is expected to go out to bid in November, with construction anticipated to begin in early spring 2026.

    Complete Streets construction will now begin in 2026, in the meantime, utility crews will continue making progress in the corridor to support the upcoming improvements. Third-party utility and communication contractors will be in the area replacing and relocating lines to prepare for future construction.

    Progress to Date:

    • More than 600 linear feet of concrete stormwater box culvert installed
    • Water main replacements completed between Logan Street and Pearl Street
    • Ongoing progress on storm main upgrades and coordination east of Pearl Street

    We appreciate your patience and understanding as we continue making vital infrastructure improvements. This expanded approach will help ensure long-term reliability, reduce future disruptions and set the stage for the upcoming Complete Streets transformation.

  • Old Hampden Update – May 2025

    Share Old Hampden Update – May 2025 on Facebook Share Old Hampden Update – May 2025 on X (formerly Twitter) Share Old Hampden Update – May 2025 on Linkedin Email Old Hampden Update – May 2025 link
    supporting image

    The City of Englewood’s contractor has completed the initial utility improvements along Old Hampden Avenue. Paving is scheduled this week, and the intersection at South Logan Street and Hampden is expected to reopen by Tuesday, May 20.

    Crews have also made significant progress on storm main upgrades, replacing outdated corrugated metal pipe with more durable concrete box culvert.

    Once the current storm main work wraps up, the closure along East Hampden will shift east. The next construction zone will close Hampden Avenue from just before South Pennsylvania Street to just before South Pearl Street. A single-lane closure will also begin just east of Pearl.

    Hospital access will be maintained throughout the project. Please follow posted detour signs in the area.

    The City of Englewood’s contractor has completed the initial utility improvements along Old Hampden Avenue. Paving is scheduled this week, and the intersection at South Logan Street and Hampden is expected to reopen by Tuesday, May 20.

    Crews have also made significant progress on storm main upgrades, replacing outdated corrugated metal pipe with more durable concrete box culvert.

    Once the current storm main work wraps up, the closure along East Hampden will shift east. The next construction zone will close Hampden Avenue from just before South Pennsylvania Street to just before South Pearl Street. A single-lane closure will also begin just east of Pearl.

    Hospital access will be maintained throughout the project. Please follow posted detour signs in the area.

Page last updated: 24 Jul 2026, 09:52 AM