Old Hampden Utility Improvements

Share Old Hampden Utility Improvements on Facebook Share Old Hampden Utility Improvements on X (formerly Twitter) Share Old Hampden Utility Improvements on Linkedin Email Old Hampden Utility Improvements link

Project Overview

Old Hampden is in need of some love, both above and below ground. This street and its aging underground water and stormwater pipelines run directly through the Wellness District of Downtown Englewood, serving Craig Hospital, Swedish Medical Center, nearby businesses and residents, office workers, and visitors with its assortment of retail stores and restaurants. Upgrading old infrastructure and enhancing public safety, accessibility and options for getting around the Old Hampden area have been key priorities for the City of Englewood and the Englewood Downtown Development Authority, as outlined through the city’s master planning process.

The Old Hampden Utility Improvements project is necessary to replace small, old 1950s-era water and stormwater pipes, manholes and infrastructure that are well past their useful life. It will prevent future water line breaks and storm-related flooding for the entire community.

Image of CCTV footage of stormwater pipe full of debris.

Aftermath of a water main break on Hampden and Washington.

The timing of each phase of the project is based on when funding is available and when contracting is finalized. To help reduce the cost of these critical infrastructure projects and limit construction-related disruptions, Englewood Utilities is working to replace the stormwater and water lines at approximately the same time.

Utility Project Phases

Phase 1: Completed January 2025 - March 2026. The first phase of stormwater system upgrades and all the water line construction was completed, with stormwater construction between South Emerson St. through S Logan St. and water line work along the entire Old Hampden Ave. corridor.

Phase 2: Scheduled from mid - August into October 2026 (six to eight weeks). Englewood Utilities is upgrading the next section of Old Hampden’s stormwater infrastructure between Grant and Lincoln streets – to the west of Swedish Medical Center. Continuation of this project is needed to reduce flooding and improve the capacity of the stormwater system. This phase of construction will be much shorter than the previous work. See below details on what to expect.

Phase 3: Planned for fall 2026, for up to three weeks. The final phase of the stormwater improvements project in this area is planned for this fall. It will temporarily close the south end of Lincoln Street adjacent to Little Dry Creek, while keeping Old Hampden partially open east-west.

Old Hampden Aug-Oct 2026 Construction: What To Expect

Construction hours: Monday through Friday, 7:00 a.m. to 4:00 p.m

Project Duration: About six to eight weeks.

Impacts:

  • Some large equipment and excavations, as well as potential noise and dust during construction hours. Crews will work to minimize impacts as much as possible.
  • No direct access to any property is expected to be cut off.
  • We are communicating directly with neighbors and businesses in the area and will provide updates online here as well.

Street Closure Info:

  • Old Hampden: Closed to traffic between Grant and Lincoln until project completion.
  • Sherman Street/Old Hampden intersection: Closed until project completion.
  • Lincoln/Hampden intersection: Closed until project completion.
  • Grant/Hampden intersection: Closed until project completion.
  • Logan/Hampden intersection: Open to north/south traffic.

Contact Information & Project Updates

For questions or concerns, please contact: Utilitiesdevreview@englewoodco.gov.

Project Overview

Old Hampden is in need of some love, both above and below ground. This street and its aging underground water and stormwater pipelines run directly through the Wellness District of Downtown Englewood, serving Craig Hospital, Swedish Medical Center, nearby businesses and residents, office workers, and visitors with its assortment of retail stores and restaurants. Upgrading old infrastructure and enhancing public safety, accessibility and options for getting around the Old Hampden area have been key priorities for the City of Englewood and the Englewood Downtown Development Authority, as outlined through the city’s master planning process.

The Old Hampden Utility Improvements project is necessary to replace small, old 1950s-era water and stormwater pipes, manholes and infrastructure that are well past their useful life. It will prevent future water line breaks and storm-related flooding for the entire community.

Image of CCTV footage of stormwater pipe full of debris.

Aftermath of a water main break on Hampden and Washington.

The timing of each phase of the project is based on when funding is available and when contracting is finalized. To help reduce the cost of these critical infrastructure projects and limit construction-related disruptions, Englewood Utilities is working to replace the stormwater and water lines at approximately the same time.

Utility Project Phases

Phase 1: Completed January 2025 - March 2026. The first phase of stormwater system upgrades and all the water line construction was completed, with stormwater construction between South Emerson St. through S Logan St. and water line work along the entire Old Hampden Ave. corridor.

Phase 2: Scheduled from mid - August into October 2026 (six to eight weeks). Englewood Utilities is upgrading the next section of Old Hampden’s stormwater infrastructure between Grant and Lincoln streets – to the west of Swedish Medical Center. Continuation of this project is needed to reduce flooding and improve the capacity of the stormwater system. This phase of construction will be much shorter than the previous work. See below details on what to expect.

Phase 3: Planned for fall 2026, for up to three weeks. The final phase of the stormwater improvements project in this area is planned for this fall. It will temporarily close the south end of Lincoln Street adjacent to Little Dry Creek, while keeping Old Hampden partially open east-west.

Old Hampden Aug-Oct 2026 Construction: What To Expect

Construction hours: Monday through Friday, 7:00 a.m. to 4:00 p.m

Project Duration: About six to eight weeks.

Impacts:

  • Some large equipment and excavations, as well as potential noise and dust during construction hours. Crews will work to minimize impacts as much as possible.
  • No direct access to any property is expected to be cut off.
  • We are communicating directly with neighbors and businesses in the area and will provide updates online here as well.

Street Closure Info:

  • Old Hampden: Closed to traffic between Grant and Lincoln until project completion.
  • Sherman Street/Old Hampden intersection: Closed until project completion.
  • Lincoln/Hampden intersection: Closed until project completion.
  • Grant/Hampden intersection: Closed until project completion.
  • Logan/Hampden intersection: Open to north/south traffic.

Contact Information & Project Updates

For questions or concerns, please contact: Utilitiesdevreview@englewoodco.gov.

  • Old Hampden Utility Improvements Update – May 2025

    Share Old Hampden Utility Improvements Update – May 2025 on Facebook Share Old Hampden Utility Improvements Update – May 2025 on X (formerly Twitter) Share Old Hampden Utility Improvements Update – May 2025 on Linkedin Email Old Hampden Utility Improvements Update – May 2025 link
    supporting image

    The City of Englewood’s contractor has completed the water main installation in Phase 1 of the project area. Crews are now working on the storm main, which includes replacing outdated corrugated metal pipe with modern concrete box culvert. So far, over 150 linear feet of culvert has been installed.

    The storm main work is expected to be completed around mid-May. At that point, the current traffic closure along East Hampden will shift east, allowing the South Logan Street and Hampden intersection to reopen. The new closure will extend along Hampden from just before South Pennsylvania Street to just before South

    The City of Englewood’s contractor has completed the water main installation in Phase 1 of the project area. Crews are now working on the storm main, which includes replacing outdated corrugated metal pipe with modern concrete box culvert. So far, over 150 linear feet of culvert has been installed.

    The storm main work is expected to be completed around mid-May. At that point, the current traffic closure along East Hampden will shift east, allowing the South Logan Street and Hampden intersection to reopen. The new closure will extend along Hampden from just before South Pennsylvania Street to just before South Pearl Street, with the Pennsylvania intersection closed to through traffic.

  • Detour Route Update – March 2025

    Share Detour Route Update – March 2025 on Facebook Share Detour Route Update – March 2025 on X (formerly Twitter) Share Detour Route Update – March 2025 on Linkedin Email Detour Route Update – March 2025 link
    supporting image

    The Old Hampden Improvements Project is advancing, and traffic patterns have been updated to accommodate ongoing work in the area.

    The intersection of Logan Street and Old Hampden Avenue will fully close again on Monday, March 3 as construction progresses. The closure on E. Hampden Avenue from S. Grant Street to S. Pennsylvania Street is estimated to last until early May.

    These closures are essential for upgrading aging infrastructure and preparing the area for streetscape improvements aimed at enhancing public safety and accessibility.

    The Old Hampden Improvements Project is advancing, and traffic patterns have been updated to accommodate ongoing work in the area.

    The intersection of Logan Street and Old Hampden Avenue will fully close again on Monday, March 3 as construction progresses. The closure on E. Hampden Avenue from S. Grant Street to S. Pennsylvania Street is estimated to last until early May.

    These closures are essential for upgrading aging infrastructure and preparing the area for streetscape improvements aimed at enhancing public safety and accessibility.

  • Detour Route Update - February 2025

    Share Detour Route Update - February 2025 on Facebook Share Detour Route Update - February 2025 on X (formerly Twitter) Share Detour Route Update - February 2025 on Linkedin Email Detour Route Update - February 2025 link
    supporting image

    The Old Hampden Improvements Project is progressing, and traffic patterns have been updated. Logan Street has reopened temporarily at Old Hampden, improving traffic flow while work continues in the area.

    What to Expect:

    • Street closures will continue in phases along Old Hampden Avenue—please follow updated detour signs and allow extra travel time.

    • Logan Street at Old Hampden is expected to fully close again in March as construction advances.

    These closures are essential for upgrading aging infrastructure and preparing the area for streetscape improvements aimed at enhancing public safety and accessibility.

    The Old Hampden Improvements Project is progressing, and traffic patterns have been updated. Logan Street has reopened temporarily at Old Hampden, improving traffic flow while work continues in the area.

    What to Expect:

    • Street closures will continue in phases along Old Hampden Avenue—please follow updated detour signs and allow extra travel time.

    • Logan Street at Old Hampden is expected to fully close again in March as construction advances.

    These closures are essential for upgrading aging infrastructure and preparing the area for streetscape improvements aimed at enhancing public safety and accessibility.

  • Bert Shuttle Route Update

    Share Bert Shuttle Route Update on Facebook Share Bert Shuttle Route Update on X (formerly Twitter) Share Bert Shuttle Route Update on Linkedin Email Bert Shuttle Route Update link
    supporting image

    Due to construction along Old Hampden Avenue, Englewood’s free shuttle service through the Wellness District has been rerouted.

    Stop 8 has been temporarily rerouted to the northwest corner of Sherman Street and Old Hampden Avenue. Stop 13 has been temporarily rerouted to the southwest corner of Pennsylvania Street and Old Hampden Avenue.

    Learn more about Englewood’s FREE bert shuttle at englewoodco.gov/bert


    Due to construction along Old Hampden Avenue, Englewood’s free shuttle service through the Wellness District has been rerouted.

    Stop 8 has been temporarily rerouted to the northwest corner of Sherman Street and Old Hampden Avenue. Stop 13 has been temporarily rerouted to the southwest corner of Pennsylvania Street and Old Hampden Avenue.

    Learn more about Englewood’s FREE bert shuttle at englewoodco.gov/bert

  • Construction Begins for Old Hampden Improvements

    Share Construction Begins for Old Hampden Improvements on Facebook Share Construction Begins for Old Hampden Improvements on X (formerly Twitter) Share Construction Begins for Old Hampden Improvements on Linkedin Email Construction Begins for Old Hampden Improvements link
    supporting image

    The City of Englewood is excited to announce the official start of the improvements on Old Hampden in the Wellness District.

    Starting Monday, January 6, 2025, crews will begin critical utility upgrades along Old Hampden Avenue, kicking off a two-phase project that will enhance the infrastructure and streetscape of this important corridor.

    The first road closure will impact E. Hampden Avenue between S. Pennsylvania Street and S. Grant Street. This section of road will be closed to through traffic as crews begin the utility work. Detours will be in place to help guide drivers around the closure. Please follow posted detour signs and allow extra time for your commute as work progresses. This closure is expected to last until late February. Afterward, rolling closures will continue along Old Hampden Avenue, moving toward S. Broadway. The sidewalk on the south side of Old Hampden will remain open for pedestrians throughout construction.

    This closure marks the start of Phase 1, which will focus on upgrading underground water, sewer, and stormwater systems to ensure reliable service for the future. Phase 1 is expected to continue through Summer 2025.

    What’s Next?

    The Old Hampden Complete Streets Project will be completed in two phases:

    • Phase 1 (January–Summer 2025): Underground utility upgrades, including the replacement of aging water, sewer and stormwater systems.
    • Phase 2 (Summer 2025–Summer 2026): Above-ground streetscape improvements, including ADA-compliant sidewalks, upgraded bus stops and traffic-calming measures. Learn more about the streetscape improvements here.

    Subscribe to this page for the most up-to-date project information and street closure information. Thank you for your patience as we work to improve Old Hampden Avenue and create a safer, more accessible corridor for all who live, work, and visit Englewood.

    The City of Englewood is excited to announce the official start of the improvements on Old Hampden in the Wellness District.

    Starting Monday, January 6, 2025, crews will begin critical utility upgrades along Old Hampden Avenue, kicking off a two-phase project that will enhance the infrastructure and streetscape of this important corridor.

    The first road closure will impact E. Hampden Avenue between S. Pennsylvania Street and S. Grant Street. This section of road will be closed to through traffic as crews begin the utility work. Detours will be in place to help guide drivers around the closure. Please follow posted detour signs and allow extra time for your commute as work progresses. This closure is expected to last until late February. Afterward, rolling closures will continue along Old Hampden Avenue, moving toward S. Broadway. The sidewalk on the south side of Old Hampden will remain open for pedestrians throughout construction.

    This closure marks the start of Phase 1, which will focus on upgrading underground water, sewer, and stormwater systems to ensure reliable service for the future. Phase 1 is expected to continue through Summer 2025.

    What’s Next?

    The Old Hampden Complete Streets Project will be completed in two phases:

    • Phase 1 (January–Summer 2025): Underground utility upgrades, including the replacement of aging water, sewer and stormwater systems.
    • Phase 2 (Summer 2025–Summer 2026): Above-ground streetscape improvements, including ADA-compliant sidewalks, upgraded bus stops and traffic-calming measures. Learn more about the streetscape improvements here.

    Subscribe to this page for the most up-to-date project information and street closure information. Thank you for your patience as we work to improve Old Hampden Avenue and create a safer, more accessible corridor for all who live, work, and visit Englewood.

  • Project Start Date

    Share Project Start Date on Facebook Share Project Start Date on X (formerly Twitter) Share Project Start Date on Linkedin Email Project Start Date link

    The Old Hampden Complete Streets Project is scheduled to begin on January 6, 2025. City staff and the contractor are currently preparing a detailed block-by-block schedule to outline when road closures and detours will occur for each phase of the project.

    To stay informed about road closures, detours and project updates, we encourage you to subscribe to this page for the latest information throughout the project.

    Thank you for your patience as we work to enhance the streetscape and infrastructure on Old Hampden.

    The Old Hampden Complete Streets Project is scheduled to begin on January 6, 2025. City staff and the contractor are currently preparing a detailed block-by-block schedule to outline when road closures and detours will occur for each phase of the project.

    To stay informed about road closures, detours and project updates, we encourage you to subscribe to this page for the latest information throughout the project.

    Thank you for your patience as we work to enhance the streetscape and infrastructure on Old Hampden.

  • October Update

    Share October Update on Facebook Share October Update on X (formerly Twitter) Share October Update on Linkedin Email October Update link

    Timber Wolf Excavating has been selected as the contractor and is in the contract approval process, work will be started in late 2024.

    Timber Wolf Excavating has been selected as the contractor and is in the contract approval process, work will be started in late 2024.

  • August Update

    Share August Update on Facebook Share August Update on X (formerly Twitter) Share August Update on Linkedin Email August Update link

    The Utilities project has been broken into three projects. The sanitary pipe will be lined independently of the main project and the pump station was also separated into its own project to ensure the work is completed by a contractor with the appropriate expertise.

    Remaining in the Old Hampden Utilities project is the replacement of the storm and water lines along the corridor as well as lining of the storm pipe on Lincoln.

    This project is wrapping up the final stages of design and plans on going out to bid around the new year.

    The Utilities project has been broken into three projects. The sanitary pipe will be lined independently of the main project and the pump station was also separated into its own project to ensure the work is completed by a contractor with the appropriate expertise.

    Remaining in the Old Hampden Utilities project is the replacement of the storm and water lines along the corridor as well as lining of the storm pipe on Lincoln.

    This project is wrapping up the final stages of design and plans on going out to bid around the new year.