Share December 2025 City Ditch Piping Project Update on Facebook
Share December 2025 City Ditch Piping Project Update on Linkedin
Email December 2025 City Ditch Piping Project Update link
HEI Civil has mobilized for the City Ditch Piping Project in Reaches 3 and 4! Crews are hard at work putting up silt fence, staking the construction area, and clearing vegetation. We also began excavating and installing pipe. Construction in Reaches 3 and 4 is anticipated to be complete by late Spring 2026.
The City Ditch Piping Project is another step forward in our ongoing efforts to improve the taste, odor and hardness of your drinking water.
Share June 2025 City Ditch Piping Project Update on Facebook
Share June 2025 City Ditch Piping Project Update on Linkedin
Email June 2025 City Ditch Piping Project Update link
Reach 1
Click on the Image to EnlargeDevelopers completed piping majority of Reach 1 following close coordination with City staff. The City is coordinating with a contractor to enclose the remaining portions of City Ditch in Reach 1. All work in Reach 1 is anticipated to be completed in 2025.
Reach 2
In 2024, the City requested a permanent easement from Burlington Northern Santa Fe Railway (BNSF) for a portion of the City Ditch Pipeline in Reach 2, which runs from Linhart Lake to Littleton Cemetery. The permanent easement would have allowed Englewood to install the pipeline in the City’s preferred alignment, minimizing impacts on the existing ditch and nearby residential areas.
BNSF unfortunately declined to grant the City a permanent easement. Reach 2 construction is on hold as the City works to redesign the piped sections that were planned to be on BNSF property outside of the City’s existing permanent easement, requiring a redesign of this reach. This adjustment will not substantially change the design for sections on the City of Littleton property, preserving parts of the existing City Ditch in this area. However, some sections of the new pipeline will be placed in the existing City Ditch channel within the City’s easement on private properties. The City will update adjacent residents and stakeholders and provide more information before construction starts, which is anticipated to begin for this reach towards the end of this year or in early 2026.
Reach 3 and 4
The City and its design engineer, Jacobs Engineering, revised the Reach 4 construction plans following a spring 2024 decision to realign the pipeline route through Belleview Park, utilizing sections of the existing City Ditch channel. The realignment addresses operation and construction challenges identified with the original proposed route. The Reach 3 plans did not substantially change over this past year.
The revised construction plans for Reach 4 are complete and the City recently issued a Request for Proposals (RFP) to select a contractor for construction on Reaches 3 and 4. Construction is expected to begin this summer.
Englewood is contacting property owners near the ditch in Reaches 3 and 4 directly to provide updates and address any potential impacts to their property during the upcoming construction.
Additional information regarding construction and other project updates will be posted to this page as it becomes available.
Share April 25, 2024 Update on Facebook
Share April 25, 2024 Update on Linkedin
Email April 25, 2024 Update link
Over the last several months, Englewood staff and the design team from Jacobs Engineering have been gathering field data, evaluating system hydraulics, and finalizing the design for the City Ditch Piping Project. As this evaluation continued for Reach 4, it was found that the initial preferred pipeline route had several barriers for construction and operation of the ditch. The pipeline alignment has been modified to generally follow the existing City Ditch alignment between S Windermere St. and the Allen Water Treatment Plant.
The redesign for this reach is in its early stages, and additional field investigation is required. Over the coming weeks, our contractors will be locating utilities and taking soil bore samples near City Ditch in Belleview Park and W Layton Ave. The contractors and their vehicles/equipment will remain within the existing City of Englewood easements, on the City of Englewood property, or within the public right-of-way. The work will be for a short duration at each location and noise will be minimal.
We appreciate your understanding and patience as we complete the design phase of this critical project for Englewood’s drinking water system. We will continue to post project updates to the Englewood Engaged page as they become available. In the meantime, if you have any questions or would like to discuss this project further, please feel free to contact us at CDPipingProject@englewoodco.gov.

Share November 23, 2023 Update on Facebook
Share November 23, 2023 Update on Linkedin
Email November 23, 2023 Update link
Englewood held a public meeting in Littleton on November 29, 2023 for neighbors living near future City Ditch Piping Project construction activities in Reaches 2 and 3. The project team reviewed the changes made since the last community meeting, shared the estimated project timeline, and discussed project next steps. Materials from the meeting have been added to this Englewood Engaged page.
Share Key Topics on Facebook
Share Key Topics on Linkedin
Email Key Topics link
The following are responses to concerns raised by members of the public following the public meetings in spring 2023. Additional communication with the public will occur over the coming months.
Tree Preservation
Englewood will coordinate with the City of Littleton to minimize impacts to trees to the extent possible while installing the City Ditch pipeline. Trees that are required to be removed to aid construction activities, or trees that would be damaged or harmed by the construction will be mitigated in accordance with the City of Littleton’s requirements for tree and vegetation replacements.
Wildlife Access to Water
While City Ditch is used year-round to convey water to the Allen Water Treatment Plant, it is an intermittent water supply that is shut down for periods of time for maintenance or other operational reasons. It is not a consistent source of water for wildlife. Wildlife have other water sources in the area since the ditch crosses multiple creeks (Lee Gulch, Slaughterhouse Gulch, Dad Clark Gulch, and Big Dry Creek). Water will continue to be available for wildlife from those sources.
Compensation
Englewood’s proposed project is consistent with both Englewood’s existing easements for City Ditch and Colorado law, which expressly allow the owners of ditch rights-of-way to engage in maintenance and improvement activities, including lining or piping the ditch. The piping project is necessary to ensure Englewood’s ability to provide a safe and reliable municipal water supply while improving the efficiency of the ditch. The work is consistent with the previous piping of other reaches of City Ditch. These activities do not provide a basis for compensating landowners.
Preserving Historical Attributes
City of Englewood is open to creating interpretative signage along the ditch to commemorate the history of City Ditch and the role it played in providing water for our community. It may be possible to preserve or move the flumes. Englewood is still determining if open ditch will remain open or be filled in. Stakeholder input indicated there is a preference for both options.
Trespassing and Safety
Homeless issues are pervasive throughout the Metro area. Enforcement of trespassing on property near City Ditch would need to be handled through the local police enforcement departments. Englewood Utilities is not equipped nor responsible for enforcing these laws.
Construction Impacts
Construction impacts will be temporary. It is estimated that active construction will last about 6-8 months in each area of pipe installation. Englewood has selected HEI Civil for this project, who has significant experience in large-diameter pipeline construction, including experience in urban and high-density areas. The City and HEI will work together with neighbors near City Ditch to ensure there is clear and early communication prior to and during construction. Englewood will work to minimize disruption. Our contractor will work closely with residents to address issues that occur.