Share Old Hampden Complete Streets Project Update - April 2025 on Facebook
Share Old Hampden Complete Streets Project Update - April 2025 on Linkedin
Email Old Hampden Complete Streets Project Update - April 2025 link
The city has received the 100% design plans from the consultant, Felsburg Holt & Ullevig. The City of Englewood Staff will review the final plans and provide feedback to FHU.
As this project is funded through a Denver Regional Council of Governments (DRCOG) grant, it requires a special sign-off process. Once approved by the Colorado Department of Transportation (CDOT), these finalized plans will be posted for contractors to submit bids in late spring/early summer. Construction is expected to begin in summer 2025 and continue through summer 2026.
Subscribe to this page for the most up-to-date project information and street closure information. Thank you for your patience as we work to improve Old Hampden Avenue and create a safer, more accessible corridor for all who live, work, and visit Englewood.
Share Detour Route Update – March 2025 on Facebook
Share Detour Route Update – March 2025 on Linkedin
Email Detour Route Update – March 2025 link
The Old Hampden Improvements Project is advancing, and traffic patterns have been updated to accommodate ongoing work in the area.
The intersection of Logan Street and Old Hampden Avenue will fully close again on Monday, March 3 as construction progresses. The closure on E. Hampden Avenue from S. Grant Street to S. Pennsylvania Street is estimated to last until early May.
These closures are essential for upgrading aging infrastructure and preparing the area for streetscape improvements aimed at enhancing public safety and accessibility.
Share Detour Route Update - February 2025 on Facebook
Share Detour Route Update - February 2025 on Linkedin
Email Detour Route Update - February 2025 link
The Old Hampden Improvements Project is progressing, and traffic patterns have been updated. Logan Street has reopened temporarily at Old Hampden, improving traffic flow while work continues in the area.
These closures are essential for upgrading aging infrastructure and preparing the area for streetscape improvements aimed at enhancing public safety and accessibility.
Share Bert Shuttle Route Update on Facebook
Share Bert Shuttle Route Update on Linkedin
Email Bert Shuttle Route Update link
Due to construction along Old Hampden Avenue, Englewood’s free shuttle service through the Wellness District has been rerouted.
Stop 8 has been temporarily rerouted to the northwest corner of Sherman Street and Old Hampden Avenue. Stop 13 has been temporarily rerouted to the southwest corner of Pennsylvania Street and Old Hampden Avenue.
Share Construction Begins for Old Hampden Improvements on Facebook
Share Construction Begins for Old Hampden Improvements on Linkedin
Email Construction Begins for Old Hampden Improvements link
The City of Englewood is excited to announce the official start of the improvements on Old Hampden in the Wellness District.
Starting Monday, January 6, 2025, crews will begin critical utility upgrades along Old Hampden Avenue, kicking off a two-phase project that will enhance the infrastructure and streetscape of this important corridor.
The first road closure will impact E. Hampden Avenue between S. Pennsylvania Street and S. Grant Street. This section of road will be closed to through traffic as crews begin the utility work. Detours will be in place to help guide drivers around the closure. Please follow posted detour signs and allow extra time for your commute as work progresses. This closure is expected to last until late February. Afterward, rolling closures will continue along Old Hampden Avenue, moving toward S. Broadway. The sidewalk on the south side of Old Hampden will remain open for pedestrians throughout construction.
This closure marks the start of Phase 1, which will focus on upgrading underground water, sewer, and stormwater systems to ensure reliable service for the future. Phase 1 is expected to continue through Summer 2025.
What’s Next?
The Old Hampden Complete Streets Project will be completed in two phases:
-
Phase 1 (January–Summer 2025): Underground utility upgrades, including the replacement of aging water, sewer, and stormwater systems.
-
Phase 2 (Summer 2025–Summer 2026): Above-ground streetscape improvements, including ADA-compliant sidewalks, upgraded bus stops, and traffic-calming measures.
Subscribe to this page for the most up-to-date project information and street closure information. Thank you for your patience as we work to improve Old Hampden Avenue and create a safer, more accessible corridor for all who live, work, and visit Englewood.
Share Construction Starting January 2025 on Facebook
Share Construction Starting January 2025 on Linkedin
Email Construction Starting January 2025 link
The Old Hampden Complete Streets Project is scheduled to begin on January 6, 2025. City staff and the contractor are currently preparing a detailed block-by-block schedule to outline when road closures and detours will occur for each phase of the project.
To stay informed about road closures, detours and project updates, we encourage you to subscribe to this page for the latest information throughout the project.
Thank you for your patience as we work to enhance the streetscape and infrastructure on Old Hampden.