Share Old Hampden Improvements Update- August on Facebook
Share Old Hampden Improvements Update- August on Linkedin
Email Old Hampden Improvements Update- August link
The next phase Old Hampden Utility Improvement Project will begin on Wednesday, August 27, 2025. This phase impacts the area from 601 to 701 E Hampden and includes the following changes:
- 601 E Hampden entrance – Closed to all traffic.
- 701 E Hampden entrance – Open for deliveries and trash collection only.
- Valet services:
- 601 E Hampden – Valet will operate from the front of the main hospital building.
- 701 E Hampden – Valet will move to the rear of the building.
The anticipated duration for this traffic control configuration is 6 to 8 weeks.
We appreciate your patience and cooperation as we complete these critical utility improvements.
Share Old Hampden Improvements Utility Project Update on Facebook
Share Old Hampden Improvements Utility Project Update on Linkedin
Email Old Hampden Improvements Utility Project Update link
Construction continues in the Phase 3 closure area from Pearl Street to Washington Street. During this time:
Access to 601 Hampden and the hospitals is being maintained via the drive lane from the east and Pennsylvania Street from the west.
Crews are actively working on the redundant water feed to the hospital to enhance system reliability.
Work in this area is expected to continue through late August 2025.
Additionally, Bid Schedule D work has been added to the contract, expanding the scope of the current project.
Thank you for your continued patience as we make these critical infrastructure improvements.
Share Bert Route Update - July 2025 on Facebook
Share Bert Route Update - July 2025 on Linkedin
Email Bert Route Update - July 2025 link
Due to construction along Old Hampden Avenue, Englewood’s free shuttle service through the Wellness District has been rerouted.
Stop 12 has been temporarily moved to to the southwest corner of S. Washington Street and Old Hampden Avenue.
View the updated route at englewoodco.gov/bert
Share Old Hampden Utility Improvements – July 2025 on Facebook
Share Old Hampden Utility Improvements – July 2025 on Linkedin
Email Old Hampden Utility Improvements – July 2025 link
Work is progressing on the Old Hampden Utility Improvements Project, and the next construction phase is scheduled to begin Tuesday, July 15.
The current closure from South Logan Street to South Pearl Street will reopen to traffic, and the closure will shift east, closing Old Hampden Avenue from South Pearl Street to South Washington Street.
Crews will continue upgrading aging utility infrastructure along the corridor, including water and stormwater pipes originally installed in the 1950s. These systems are nearing the end of their useful life and have contributed to water main breaks and storm-related flooding in the area.

Share Old Hampden Utility Improvements Timeline Extended on Facebook
Share Old Hampden Utility Improvements Timeline Extended on Linkedin
Email Old Hampden Utility Improvements Timeline Extended link
As utility work continues along Old Hampden Avenue, the City of Englewood is adjusting the construction timeline to allow for a more efficient and coordinated approach. Multiple new phases will be added to the utility portion of the project, pending city council approval. This additional work ensures that the entire length of aged and decaying storm pipe will be replaced prior to the Complete Streets construction, reducing the risk of failure of old pipe under new improvements, limiting the need to revisit completed areas and minimizing disruption to surrounding businesses, hospitals and residents.
The Complete Streets streetscape improvements originally planned to begin this fall will now be postponed. The project is expected to go out to bid in November, with construction anticipated to begin in early spring 2026.
Complete Streets construction will now begin in 2026, in the meantime, utility crews will continue making progress in the corridor to support the upcoming improvements. Third-party utility and communication contractors will be in the area replacing and relocating lines to prepare for future construction.
Progress to Date:
- More than 600 linear feet of concrete stormwater box culvert installed
- Water main replacements completed between Logan Street and Pearl Street
- Ongoing progress on storm main upgrades and coordination east of Pearl Street
We appreciate your patience and understanding as we continue making vital infrastructure improvements. This expanded approach will help ensure long-term reliability, reduce future disruptions and set the stage for the upcoming Complete Streets transformation.
Share Old Hampden Utility Improvements Update – May 2025 on Facebook
Share Old Hampden Utility Improvements Update – May 2025 on Linkedin
Email Old Hampden Utility Improvements Update – May 2025 link
The City of Englewood’s contractor has completed the initial utility improvements along Old Hampden Avenue. Paving is scheduled this week, and the intersection at South Logan Street and Hampden is expected to reopen by Tuesday, May 20.
Crews have also made significant progress on storm main upgrades, replacing outdated corrugated metal pipe with more durable concrete box culvert.
Once the current storm main work wraps up, the closure along East Hampden will shift east. The next construction zone will close Hampden Avenue from just before South Pennsylvania Street to just before South Pearl Street. A single-lane closure will also begin just east of Pearl.
Hospital access will be maintained throughout the project. Please follow posted detour signs in the area.
Share Old Hampden Complete Streets Project Update - April 2025 on Facebook
Share Old Hampden Complete Streets Project Update - April 2025 on Linkedin
Email Old Hampden Complete Streets Project Update - April 2025 link
The city has received the 100% design plans from the consultant, Felsburg Holt & Ullevig. The City of Englewood Staff will review the final plans and provide feedback to FHU.
As this project is funded through a Denver Regional Council of Governments (DRCOG) grant, it requires a special sign-off process. Once approved by the Colorado Department of Transportation (CDOT), these finalized plans will be posted for contractors to submit bids in late spring/early summer. Construction is expected to begin in summer 2025 and continue through summer 2026.
Subscribe to this page for the most up-to-date project information and street closure information. Thank you for your patience as we work to improve Old Hampden Avenue and create a safer, more accessible corridor for all who live, work, and visit Englewood.
Share Detour Route Update – March 2025 on Facebook
Share Detour Route Update – March 2025 on Linkedin
Email Detour Route Update – March 2025 link
The Old Hampden Improvements Project is advancing, and traffic patterns have been updated to accommodate ongoing work in the area.
The intersection of Logan Street and Old Hampden Avenue will fully close again on Monday, March 3 as construction progresses. The closure on E. Hampden Avenue from S. Grant Street to S. Pennsylvania Street is estimated to last until early May.
These closures are essential for upgrading aging infrastructure and preparing the area for streetscape improvements aimed at enhancing public safety and accessibility.
Share Detour Route Update - February 2025 on Facebook
Share Detour Route Update - February 2025 on Linkedin
Email Detour Route Update - February 2025 link
The Old Hampden Improvements Project is progressing, and traffic patterns have been updated. Logan Street has reopened temporarily at Old Hampden, improving traffic flow while work continues in the area.
These closures are essential for upgrading aging infrastructure and preparing the area for streetscape improvements aimed at enhancing public safety and accessibility.
Share Bert Shuttle Route Update on Facebook
Share Bert Shuttle Route Update on Linkedin
Email Bert Shuttle Route Update link
Due to construction along Old Hampden Avenue, Englewood’s free shuttle service through the Wellness District has been rerouted.
Stop 8 has been temporarily rerouted to the northwest corner of Sherman Street and Old Hampden Avenue. Stop 13 has been temporarily rerouted to the southwest corner of Pennsylvania Street and Old Hampden Avenue.