US-285 & S Broadway Project

Share US-285 & S Broadway Project on Facebook Share US-285 & S Broadway Project on Twitter Share US-285 & S Broadway Project on Linkedin Email US-285 & S Broadway Project link

Project Overview

The US-285 & S. Broadway Interchange Reconstruction project will reconstruct the S. Broadway bridge over 285, the adjacent ramps, and US-285 itself from approximately Bannock St to Sherman St. The project will replace the aging and outdated bridge, improve roadway geometry, and improve pedestrian and bicycle facilities within the interchange.

Project Schedule

The design phase started in December of 2020 and was completed in early 2022. The project was initially advertised for construction in June of 2022 and the bid opening held on July 26, 2022. Due to unexpectedly high bids, construction cannot start until additional funding is identified for the project.

Proposed Improvements

Interchange Configuration

The consultant worked with the City and CDOT to develop and review possible interchange configurations. Ultimately, the analysis resulted in the recommendation and selection of a tight diamond interchange, similar to what exists today. Compared to the existing interchange, the proposed interchange will feature:

  • Improved roadway geometry compared to the existing diamond
  • Improved storage space for northbound left turning traffic
  • Safer crossings with fewer conflicts between pedestrians and traffic at each crossing
  • Provides more accessible greenspace by shifting the ramps closer to US-285
  • Maintains a similar footprint which eliminates the need to acquire private right-of-way

Roadway Geometry Improvements

The new interchange will include 3 through lanes in each direction on US-285, while improving roadway geometry to meet modern standards for driver and pedestrian safety and comfort. The new interchange will modify the curve on US-285 to provide a more predictable and comfortable driver experience. The ramps will be designed to provide softer departure angles. The signalized intersection at US-285 & S. Sherman St will be removed to eliminate hazardous conflicts between US-285 traffic, S. Sherman traffic, and merging traffic to and from S. Broadway. The new geometry at Sherman St will only allow the option of traffic making a right turn from westbound US-285 to northbound Sherman St.


Bridge Replacement

The existing S Broadway bridge over US-285 is over 70 years old and does not meet modern design standards for roadways such as vertical clearances, appropriate lines of sights, and shoulders. This project will replace the outdated and deteriorating structure with a longer bridge to accommodate the additional lanes underneath. The bridge replacement gives the City the opportunity to improve on other sub-standard features on the S Broadway cross-section as well. Such improvements may include: an improved pedestrian and bicycle experience through wider sidewalks and a buffer zone between pedestrian and vehicle traffic, improved aesthetics on a keynote piece of infrastructure in the downtown district, and narrower lanes promoting safer driving as traffic enters the pedestrian dense downtown district.

Retaining Walls

As part of the bridge replacement the existing retaining walls will be removed. The new retaining walls will consist of short, cheap walls arranged in a stepped configuration to make up the elevation difference between US-285 & S. Broadway. In addition to a lower up front cost, these walls are easier to access and maintain, providing cost savings throughout the life-cycle of the new interchange.

Drainage

The additional lanes on US-285 will add more surface run-off that will need to be collected and responsibly discharged into the nearby Little Dry Creek. The proposed storm sewer system has a higher capacity than the existing system and incorporates storm water quality features including rain gardens and hydrodynamic separators.

Multi-Modal

The multi-modal improvements made through this project will be subtle, yet impactful. The types of bicycle and pedestrian facilities will remain primarily the same throughout the project, however, key changes will be made to improve the pedestrian and bicycle experience. The project incorporates the following characteristics to improve bicycle and pedestrian safety and comfort:

  • Wider sidewalks on the S Broadway bridge
  • Buffer zones between pedestrian and vehicle traffic wherever possible
  • Improved overall aesthetic of the interchange
  • Leading pedestrian intervals in the traffic signal phasing
  • Roadway geometry that slows right turning traffic and provides higher pedestrian visibility
  • Pedestrian refuge islands that shorten crossings and reduce the number of conflicts in a giving crosswalk

Aesthetic Improvements

The project will make significant changes to the visual characteristics of the interchange. The new bridge will incorporate prominent gateway features in the form of bookend columns with a large City of Englewood facing US-285 traffic. The bridge and retaining walls will feature colored and textured concrete to further draw attention to the city’s downtown district.


Project Funding

This project has three sources of funding. Federal funds awarded via a grant through the DRCOG Transportation Improvement Program, State Funds, and City of Englewood funds. The funding breakdown is as follows:

$7.6M (Federal Grant) + $3.1M (CDOT) + $4.2M (City of Englewood) = $14.9M

Project Overview

The US-285 & S. Broadway Interchange Reconstruction project will reconstruct the S. Broadway bridge over 285, the adjacent ramps, and US-285 itself from approximately Bannock St to Sherman St. The project will replace the aging and outdated bridge, improve roadway geometry, and improve pedestrian and bicycle facilities within the interchange.

Project Schedule

The design phase started in December of 2020 and was completed in early 2022. The project was initially advertised for construction in June of 2022 and the bid opening held on July 26, 2022. Due to unexpectedly high bids, construction cannot start until additional funding is identified for the project.

Proposed Improvements

Interchange Configuration

The consultant worked with the City and CDOT to develop and review possible interchange configurations. Ultimately, the analysis resulted in the recommendation and selection of a tight diamond interchange, similar to what exists today. Compared to the existing interchange, the proposed interchange will feature:

  • Improved roadway geometry compared to the existing diamond
  • Improved storage space for northbound left turning traffic
  • Safer crossings with fewer conflicts between pedestrians and traffic at each crossing
  • Provides more accessible greenspace by shifting the ramps closer to US-285
  • Maintains a similar footprint which eliminates the need to acquire private right-of-way

Roadway Geometry Improvements

The new interchange will include 3 through lanes in each direction on US-285, while improving roadway geometry to meet modern standards for driver and pedestrian safety and comfort. The new interchange will modify the curve on US-285 to provide a more predictable and comfortable driver experience. The ramps will be designed to provide softer departure angles. The signalized intersection at US-285 & S. Sherman St will be removed to eliminate hazardous conflicts between US-285 traffic, S. Sherman traffic, and merging traffic to and from S. Broadway. The new geometry at Sherman St will only allow the option of traffic making a right turn from westbound US-285 to northbound Sherman St.


Bridge Replacement

The existing S Broadway bridge over US-285 is over 70 years old and does not meet modern design standards for roadways such as vertical clearances, appropriate lines of sights, and shoulders. This project will replace the outdated and deteriorating structure with a longer bridge to accommodate the additional lanes underneath. The bridge replacement gives the City the opportunity to improve on other sub-standard features on the S Broadway cross-section as well. Such improvements may include: an improved pedestrian and bicycle experience through wider sidewalks and a buffer zone between pedestrian and vehicle traffic, improved aesthetics on a keynote piece of infrastructure in the downtown district, and narrower lanes promoting safer driving as traffic enters the pedestrian dense downtown district.

Retaining Walls

As part of the bridge replacement the existing retaining walls will be removed. The new retaining walls will consist of short, cheap walls arranged in a stepped configuration to make up the elevation difference between US-285 & S. Broadway. In addition to a lower up front cost, these walls are easier to access and maintain, providing cost savings throughout the life-cycle of the new interchange.

Drainage

The additional lanes on US-285 will add more surface run-off that will need to be collected and responsibly discharged into the nearby Little Dry Creek. The proposed storm sewer system has a higher capacity than the existing system and incorporates storm water quality features including rain gardens and hydrodynamic separators.

Multi-Modal

The multi-modal improvements made through this project will be subtle, yet impactful. The types of bicycle and pedestrian facilities will remain primarily the same throughout the project, however, key changes will be made to improve the pedestrian and bicycle experience. The project incorporates the following characteristics to improve bicycle and pedestrian safety and comfort:

  • Wider sidewalks on the S Broadway bridge
  • Buffer zones between pedestrian and vehicle traffic wherever possible
  • Improved overall aesthetic of the interchange
  • Leading pedestrian intervals in the traffic signal phasing
  • Roadway geometry that slows right turning traffic and provides higher pedestrian visibility
  • Pedestrian refuge islands that shorten crossings and reduce the number of conflicts in a giving crosswalk

Aesthetic Improvements

The project will make significant changes to the visual characteristics of the interchange. The new bridge will incorporate prominent gateway features in the form of bookend columns with a large City of Englewood facing US-285 traffic. The bridge and retaining walls will feature colored and textured concrete to further draw attention to the city’s downtown district.


Project Funding

This project has three sources of funding. Federal funds awarded via a grant through the DRCOG Transportation Improvement Program, State Funds, and City of Englewood funds. The funding breakdown is as follows:

$7.6M (Federal Grant) + $3.1M (CDOT) + $4.2M (City of Englewood) = $14.9M

  • 3.2.21 - Project Update

    Share 3.2.21 - Project Update on Facebook Share 3.2.21 - Project Update on Twitter Share 3.2.21 - Project Update on Linkedin Email 3.2.21 - Project Update link

    US-285 & S. Broadway Users,

    This email is the second in a series of monthly updates regarding the US-285 & S. Broadway Interchange Reconstruction Project.

    In the last month, the project team continued work on establishing existing conditions. The geotechnical team performed soil borings and began analyzing the site’s subsurface conditions, the environmental team began field investigations for historic resources, and the traffic team is nearly finished with analyzing the existing traffic conditions and crash data. The project team hosted the project’s first public information meeting on Thursday, February 18th via live stream on Microsoft Teams. The project team received great questions and comments during the meeting and this feedback will be closely considered as the design progresses. A link to a recording of the meeting can be found HERE.

    Going forward, surveying, topographic mapping, and determining existing right-of-way boundaries will be completed. The team will take a closer look at each of the proposed alternatives, comparing things like cost, safety, constructability, and how well the alternatives meet the goals of the project. The team will also be in the field marking and locating existing underground utilities. The next public information meeting is tentatively scheduled for May 2021.

    As always, please feel free to reach out to the City’s Project Manager, Jake Warren at jwarren@englewoodco.gov.

    Best,
    Englewood Public Works


  • 2.18.21 - Link to Recording of Meeting

    Share 2.18.21 - Link to Recording of Meeting on Facebook Share 2.18.21 - Link to Recording of Meeting on Twitter Share 2.18.21 - Link to Recording of Meeting on Linkedin Email 2.18.21 - Link to Recording of Meeting link

    Public Information Meeting Recording – February 18th, 2021

    Hello Englewood,

    Thank you to those who participated in the Public Information Meeting. We apologize for the technical difficulties that occurred causing us to restart the stream and lose some of the participants. We understand the importance of sharing information about the project and soliciting feedback from the public. With that in mind, please use the link below to access a recording of the meeting and feel free to reach out to the City’s Project Manager, Jake Warren via email at jwarren@englewoodco.gov.

    CLICK HERE TO VIEW A RECORDING OF THE MEETING

    The next public meeting for the project is tentatively scheduled for May 2021. At this meeting, the team plans to share the findings of the Traffic Study, Environmental Investigations, and Alternatives Analysis while soliciting additional feedback on the preferred alternative.

    Keep a lookout for additional email updates as the project progresses!

    - Englewood Public Works Department

  • 2.17.21 - Virtual Public Information Link

    Share 2.17.21 - Virtual Public Information Link on Facebook Share 2.17.21 - Virtual Public Information Link on Twitter Share 2.17.21 - Virtual Public Information Link on Linkedin Email 2.17.21 - Virtual Public Information Link link

    Hello Englewood,

    The City will be hosting a Virtual Public Information Meeting for the US-285 & S Broadway Project this Thursday (2/18/2021) at 6 p.m. The meeting will be held via Microsoft Teams Live Events, which can be accessed through your web browser. The meeting will consist of a presentation by the project team as well as an opportunity to ask questions and provide feedback. Please use the link below to access the meeting.

    LINK TO MEETING

    Review this PDF document with exhibits at your leisure. These exhibits are intended to help you understand specific characteristics of the project and to help you to prepare any questions in advance of the meeting.

    We look forward to sharing more about the project with you on Thursday!

    - Englewood Public Works Department

  • 2.3.21 - Project Update

    Share 2.3.21 - Project Update on Facebook Share 2.3.21 - Project Update on Twitter Share 2.3.21 - Project Update on Linkedin Email 2.3.21 - Project Update link

    US-285 & S Broadway Users,

    This email is the first in a series of monthly updates regarding the US-285 & S Broadway Interchange Reconstruction Project.

    Work thus far has been focused on establishing existing conditions and developing models to inform decisions later in the design process. Since starting, the traffic team has coordinated with CDOT to establish traffic analysis procedures, gather traffic counts and crash data, and develop a model of the current traffic conditions. The survey team has completed a lidar survey and continues gathering supplementary survey data. The drainage and water quality team continues gathering data on existing drainage characteristics to assist the generation of a hydraulic model. The environmental team is working with CDOT and the State Historic Preservation Office to identify any historically significant properties or infrastructure near the interchange. Lastly, the utilities team is compiling as-builts and GIS information on the existing subsurface utilities.

    Also note, the City will be hosting a Virtual Public Meeting for the project on February 18th, at 6 P.M. More information, as well as a link/invitation, will be sent out a few days prior to the meeting.

  • 1.25.21 - Virtual Public Meeting #1 Announcement

    Share 1.25.21 - Virtual Public Meeting #1 Announcement on Facebook Share 1.25.21 - Virtual Public Meeting #1 Announcement on Twitter Share 1.25.21 - Virtual Public Meeting #1 Announcement on Linkedin Email 1.25.21 - Virtual Public Meeting #1 Announcement link

    Hey Englewood,

    The City is planning for a major reconstruction of the US-285 & S Broadway Interchange. If you would like to learn more about the project and have the opportunity to ask questions, please join us for our first Public Information Meeting. The City of Englewood will host a Virtual Public Information Meeting for this project on Thursday, February 18, 2021, at 6:00 p.m. An invitation/ hyperlink will be published on the webpage and shared to the email list prior to the meeting.

    - Englewood Public Works Department

  • US-285 & S Broadway Project Newsfeed

    Share US-285 & S Broadway Project Newsfeed on Facebook Share US-285 & S Broadway Project Newsfeed on Twitter Share US-285 & S Broadway Project Newsfeed on Linkedin Email US-285 & S Broadway Project Newsfeed link

    Keep up-to-date on news and updates that happen throughout the project.

Page last updated: 07 Sep 2023, 09:47 AM