Project Description
The City of Englewood is working with Goodbee and Associates and Elite Industries to enhance Emerson Park, including new play features, the addition of a picnic shelter, and upgrades to the landscape and pathways. These enhancements aim to create a more inviting and functional outdoor space for community members to enjoy. The southeast section will be temporarily closed during irrigation replacement and sidewalk widening.
Estimated Cost of Improvements $600,000
Project Update
As part of the city’s Renew & Recreate renovations, Emerson Park is complete! The park’s updated design reflects neighborhood feedback, ensuring the improvements reflect what community members wanted to see in their park. A ribbon-cutting ceremony celebrating the completed renovations took place on October 17, 2026.
In March 2017, Englewood City Council adopted the Parks and Recreation Master Plan to serve as a road map for future park development/redevelopment and provide a balance of facilities, amenities and recreation programs for the next 10 years.
In July 2023, the Department of Parks, Recreation, Library and Golf updated the 2017 Master Plan Recommendations Sections (Chapter 3) to outline key improvements to Englewood's parks, open spaces and facilities to meet the current needs and issues of the community.
The City of Englewood is working with Goodbee and Associates and Elite Industries to enhance Emerson Park, including new play features, the addition of a picnic shelter, and upgrades to the landscape and pathways. These enhancements aim to create a more inviting and functional outdoor space for community members to enjoy. The southeast section will be temporarily closed during irrigation replacement and sidewalk widening.
Estimated Cost of Improvements $600,000
Project Update
As part of the city’s Renew & Recreate renovations, Emerson Park is complete! The park’s updated design reflects neighborhood feedback, ensuring the improvements reflect what community members wanted to see in their park. A ribbon-cutting ceremony celebrating the completed renovations took place on October 17, 2026.
In March 2017, Englewood City Council adopted the Parks and Recreation Master Plan to serve as a road map for future park development/redevelopment and provide a balance of facilities, amenities and recreation programs for the next 10 years.
In July 2023, the Department of Parks, Recreation, Library and Golf updated the 2017 Master Plan Recommendations Sections (Chapter 3) to outline key improvements to Englewood's parks, open spaces and facilities to meet the current needs and issues of the community.
Share October Update: Emerson Park Renovations Complete on FacebookShare October Update: Emerson Park Renovations Complete on X (formerly Twitter)Share October Update: Emerson Park Renovations Complete on LinkedinEmail October Update: Emerson Park Renovations Complete link
As part of the city’s Renew & Recreate renovations, Emerson Park is complete! The park’s updated design reflects neighborhood feedback, ensuring the improvements reflect what community members wanted to see in their park. A ribbon-cutting ceremony celebrating the completed renovations took place on October 17, 2026.
As part of the city’s Renew & Recreate renovations, Emerson Park is complete! The park’s updated design reflects neighborhood feedback, ensuring the improvements reflect what community members wanted to see in their park. A ribbon-cutting ceremony celebrating the completed renovations took place on October 17, 2026.
Share September 2026 Update on FacebookShare September 2026 Update on X (formerly Twitter)Share September 2026 Update on LinkedinEmail September 2026 Update link
Emerson Park improvements are nearly complete!
Most of the improvements at Emerson Park are now in place, including new play features, trees, a widened sidewalk, landscaping and irrigation upgrades. The pergola is the final piece of the project and is planned for installation in the coming weeks.
Installation is expected to take approximately two to three weeks. During construction, only the pergola installation area will be closed. The grass and playground will remain open for community members to enjoy.
Stay tuned for details on an upcoming ribbon-cutting ceremony to celebrate the finished project!
Emerson Park improvements are nearly complete!
Most of the improvements at Emerson Park are now in place, including new play features, trees, a widened sidewalk, landscaping and irrigation upgrades. The pergola is the final piece of the project and is planned for installation in the coming weeks.
Installation is expected to take approximately two to three weeks. During construction, only the pergola installation area will be closed. The grass and playground will remain open for community members to enjoy.
Stay tuned for details on an upcoming ribbon-cutting ceremony to celebrate the finished project!
Share May 2026 Update on FacebookShare May 2026 Update on X (formerly Twitter)Share May 2026 Update on LinkedinEmail May 2026 Update link
Emerson Park is taking shape!
New play features and trees are now installed, the sidewalk has been widened, and more improvements are on the way, including a picnic shelter and upgrades to the landscaping. These enhancements aim to create a more inviting and functional outdoor space for community members to enjoy. The park is scheduled to open in early summer 2026.
Emerson Park is taking shape!
New play features and trees are now installed, the sidewalk has been widened, and more improvements are on the way, including a picnic shelter and upgrades to the landscaping. These enhancements aim to create a more inviting and functional outdoor space for community members to enjoy. The park is scheduled to open in early summer 2026.
Share February 2026 Update on FacebookShare February 2026 Update on X (formerly Twitter)Share February 2026 Update on LinkedinEmail February 2026 Update link
The southeast section of the park is temporarily closed while crews complete irrigation replacement and sidewalk widening. This area is expected to open the week of February 16. Additional improvements include new play features, a picnic shelter and upgrades to landscape and pathways. Construction is expected to be completed this summer.
The southeast section of the park is temporarily closed while crews complete irrigation replacement and sidewalk widening. This area is expected to open the week of February 16. Additional improvements include new play features, a picnic shelter and upgrades to landscape and pathways. Construction is expected to be completed this summer.
Share November 2025 Update on FacebookShare November 2025 Update on X (formerly Twitter)Share November 2025 Update on LinkedinEmail November 2025 Update link
Update 11/20: Construction for Emerson Park, originally scheduled to start the week of November 24, has been delayed due to permitting requirements. A new start date will be provided once finalized.
Improvements for Emerson Park will include:
New play features
The addition of a picnic shelter
Upgrades to the landscaping and pathways
The west side of the park will be closed during construction, while the smaller section east of South Emerson Street will remain open. Construction is expected be completed by summer 2026.
Update 11/20: Construction for Emerson Park, originally scheduled to start the week of November 24, has been delayed due to permitting requirements. A new start date will be provided once finalized.
Improvements for Emerson Park will include:
New play features
The addition of a picnic shelter
Upgrades to the landscaping and pathways
The west side of the park will be closed during construction, while the smaller section east of South Emerson Street will remain open. Construction is expected be completed by summer 2026.
Share August 2025 Update on FacebookShare August 2025 Update on X (formerly Twitter)Share August 2025 Update on LinkedinEmail August 2025 Update link
Emerson Park’s construction contract is set for city council approval on Monday, September 15, along with two other bond project contracts.
The same contractor is also working on Cushing Park. Due to this conflict, construction at Emerson Park will now start in early winter 2026 with an anticipated completion by summer 2026.
Emerson Park’s construction contract is set for city council approval on Monday, September 15, along with two other bond project contracts.
The same contractor is also working on Cushing Park. Due to this conflict, construction at Emerson Park will now start in early winter 2026 with an anticipated completion by summer 2026.
Over the next three years and beyond, $41.5 million will be invested in parks and recreation through the bond projects approved by Englewood voters. General Obligation Bonds require 85% of the work to be completed within three years, so the majority of projects are expected to be finished by 2028.
Thanks to your support, the city is investing in vibrant parks and recreation for everyone, now and into the future, through the Renew & Recreate campaign. Funded by the Parks and Recreation Bond, this initiative includes major upgrades to parks, playgrounds, recreation facilities and trails.