Dartmouth Avenue Bridge Widening Project
Project Description
The City of Englewood has awarded a construction contract to Jalisco International to widen and rehabilitate the Dartmouth Avenue bridge over the South Platte River. The bridge will be widened approximately fifteen feet to accommodate an additional drive lane and include a new five foot wide sidewalk on the south side. Roadway surface improvements will include an asphalt mill and overlay of Dartmouth Avenue from Santa Fe to S Platte River Drive. Intersection improvements including new traffic signals will be completed on both sides of the widened bridge. Construction phasing will be utilized to keep two lanes of traffic open during the life of the project. Phase 1 will have two lanes of traffic open on the south side of the bridge while the north side of the bridge deck is replaced. Phase 2 will open one lane of traffic on the north side of the bridge and one lane of traffic on the south side of the bridge while the middle of the bridge deck is replaced. The final phases will have traffic on the north side of the bridge while the south side of the bridge deck is replaced, and the structure is widened.
Timeline
The Dartmouth Bridge project has been delayed due to 3rd party construction delays related to the project. Currently, contractors are focused on finishing the substructure units on the south side of the bridge. Once this phase is complete, the installation of girders and the final stages involving the deck, sidewalk, and rail can proceed. Delays stemming from third-party utilities have extended the anticipated project completion date from summer 2024 to winter 2025.
Project Description
The City of Englewood has awarded a construction contract to Jalisco International to widen and rehabilitate the Dartmouth Avenue bridge over the South Platte River. The bridge will be widened approximately fifteen feet to accommodate an additional drive lane and include a new five foot wide sidewalk on the south side. Roadway surface improvements will include an asphalt mill and overlay of Dartmouth Avenue from Santa Fe to S Platte River Drive. Intersection improvements including new traffic signals will be completed on both sides of the widened bridge. Construction phasing will be utilized to keep two lanes of traffic open during the life of the project. Phase 1 will have two lanes of traffic open on the south side of the bridge while the north side of the bridge deck is replaced. Phase 2 will open one lane of traffic on the north side of the bridge and one lane of traffic on the south side of the bridge while the middle of the bridge deck is replaced. The final phases will have traffic on the north side of the bridge while the south side of the bridge deck is replaced, and the structure is widened.
Timeline
The Dartmouth Bridge project has been delayed due to 3rd party construction delays related to the project. Currently, contractors are focused on finishing the substructure units on the south side of the bridge. Once this phase is complete, the installation of girders and the final stages involving the deck, sidewalk, and rail can proceed. Delays stemming from third-party utilities have extended the anticipated project completion date from summer 2024 to winter 2025.
-
Eastbound Dartmouth Closure Extended
Share Eastbound Dartmouth Closure Extended on Facebook Share Eastbound Dartmouth Closure Extended on Twitter Share Eastbound Dartmouth Closure Extended on Linkedin Email Eastbound Dartmouth Closure Extended linkEastbound Dartmouth Avenue will remain closed through at least Tuesday, March 11, as crews continue prepping the road for the widening project. Closures will be in place Monday through Friday from 7 a.m. to 5 p.m., with the road reopening on weekends.
This project is widening and rehabilitating the Dartmouth Avenue bridge to enhance safety and mobility. Once complete, it will feature an additional drive lane, a new sidewalk on the south side, improved roadway surfaces, and upgraded traffic signals. We appreciate your patience during this work!
-
Dartmouth Avenue Closure
Share Dartmouth Avenue Closure on Facebook Share Dartmouth Avenue Closure on Twitter Share Dartmouth Avenue Closure on Linkedin Email Dartmouth Avenue Closure linkEastbound Dartmouth Avenue will be closed on Friday, February 21 from 8 a.m. to at least 4 p.m. between S. Platte River Drive and Santa Fe as part of the Dartmouth Bridge Widening Project. Crews will be installing a streetlight on the east corridor.This project is widening and rehabilitating the Dartmouth Avenue Bridge to improve traffic flow and pedestrian safety. The improvements include an additional drive lane, a new sidewalk on the south side, upgraded roadway surfaces and new traffic signals at both ends of the bridge. The project is expected to be completed by spring 2025. -
Dartmouth Avenue Closed Feb. 17 & 18
Share Dartmouth Avenue Closed Feb. 17 & 18 on Facebook Share Dartmouth Avenue Closed Feb. 17 & 18 on Twitter Share Dartmouth Avenue Closed Feb. 17 & 18 on Linkedin Email Dartmouth Avenue Closed Feb. 17 & 18 linkUpdate 2/17/25: Eastbound Dartmouth Avenue will be closed from 8 a.m. to 4 p.m. on Tuesday, February 18, between S. Platte River Drive and Santa Fe for continued work in the area.
Eastbound Dartmouth Avenue will be closed on Monday, February 17, from 7 a.m. to 5 p.m. between S Platte River Drive and Santa Fe for excavation work as part of Dartmouth Avenue Bridge widening project.
-
Dartmouth Bridge Closure - January 30
Share Dartmouth Bridge Closure - January 30 on Facebook Share Dartmouth Bridge Closure - January 30 on Twitter Share Dartmouth Bridge Closure - January 30 on Linkedin Email Dartmouth Bridge Closure - January 30 linkThe Dartmouth Avenue bridge will be closed in both directions tomorrow, Thursday, January 30, from 9 a.m. to 3 p.m. for the installation of signs in the area. Please follow posted detour routes and plan extra travel time. Thank you for your patience as we continue improvements in the area!
-
Eastbound Dartmouth Closure January 17
Share Eastbound Dartmouth Closure January 17 on Facebook Share Eastbound Dartmouth Closure January 17 on Twitter Share Eastbound Dartmouth Closure January 17 on Linkedin Email Eastbound Dartmouth Closure January 17 linkEastbound Dartmouth Avenue will be closed between S. Platte River Drive and Santa Fe on Friday, January 17, from 8 a.m. to approximately 4 p.m. for concrete and driveway work, further preparing the area for the widening of the eastbound Dartmouth lanes.
-
Dartmouth Ave. Closure - December 23, 2024
Share Dartmouth Ave. Closure - December 23, 2024 on Facebook Share Dartmouth Ave. Closure - December 23, 2024 on Twitter Share Dartmouth Ave. Closure - December 23, 2024 on Linkedin Email Dartmouth Ave. Closure - December 23, 2024 linkEastbound Dartmouth will be closed between the S. Platte River Dr. and Santa Fe on Monday, December 23, from 8 a.m. to approximately 4 p.m. Crews will be prepping the area for excavation to widen the roadway, one of the final steps to complete the Dartmouth Bridge Project.
-
Dartmouth Bridge Closure Nov. 11 - 17
Share Dartmouth Bridge Closure Nov. 11 - 17 on Facebook Share Dartmouth Bridge Closure Nov. 11 - 17 on Twitter Share Dartmouth Bridge Closure Nov. 11 - 17 on Linkedin Email Dartmouth Bridge Closure Nov. 11 - 17 linkUpdate: Due to weather, the Dartmouth Avenue Bridge closure originally scheduled for November 4-8 has been delayed to November 11-17.
Crews have begun the mill and overlay process on the westbound lanes east of the bridge as part of ongoing roadway improvements. Please note that the bridge will be closed from November 11 through November 17 to allow crews to complete the surface of the bridge deck.Once utility work in the eastbound lanes is completed, work will proceed on the widened portion of the roadway between the bridge and Santa Fe. The eastbound lanes will then be paved, marking the final stages of the project. This project is on schedule to be completed by the end of 2024.
-
Dartmouth Bridge Closure - October 15
Share Dartmouth Bridge Closure - October 15 on Facebook Share Dartmouth Bridge Closure - October 15 on Twitter Share Dartmouth Bridge Closure - October 15 on Linkedin Email Dartmouth Bridge Closure - October 15 linkDartmouth Bridge will be closed today, October 15, until 4 p.m. as crews apply new temporary pavement and hang mast arms for the traffic signals.
This project is set to be completed later this year and will help with traffic safety and congestion in the area.
-
Dartmouth Bridge Closure 9/26-10/1
Share Dartmouth Bridge Closure 9/26-10/1 on Facebook Share Dartmouth Bridge Closure 9/26-10/1 on Twitter Share Dartmouth Bridge Closure 9/26-10/1 on Linkedin Email Dartmouth Bridge Closure 9/26-10/1 linkDartmouth Bridge will be closed from September 26 to October 1 as crews pour the final section of the widened deck. The closure will allow time for the deck to fully cure before reopening to traffic. Please plan your routes accordingly!
Plan ahead and stay up-to-date by checking the latest road construction map at englewoodco.gov/construction. -
Road Closures
Share Road Closures on Facebook Share Road Closures on Twitter Share Road Closures on Linkedin Email Road Closures linkRoad Closures
8/27/24 Update:
The Dartmouth Bridge will be closed in both directions from Thursday, August 29 through at least Friday, August 30. Girders will be set in place during this closure.
4/25/24 Update:
East S. Platte River Drive will be closed in both directions just south of Dartmouth Avenue from Monday, April 29 to Wednesday, May 1 to assemble a crane for the Dartmouth Bridge Widening Project.
This project is set to be completed later this year and will help with traffic safety and congestion in the area.3/27/24 Update:
Dartmouth Bridge will be closed starting Friday, March 29 at 8 a.m. until at least Wednesday, April 3 to complete a concrete deck pour. Avoid the area if possible, take an alternate route or use the detour south to Hamilton Place.3/20/24 Update:
Westbound lanes across Dartmouth Bridge will be closed on March 20, 21 and 25.2/26/24 Update:
Westbound lanes across Dartmouth Bridge will be closed starting tomorrow, February 27 until at least Friday, March 1.1/23/24 Update:
Dartmouth Bridge will be closed starting today, January 23 to at least Friday, January 26. Avoid the area if possible, take an alternate route or use the detour south to Hamilton Place.12/14/23 Update:
The Dartmouth Bridge will be closed December 15, to switch traffic over to both lanes on the north side of the bridge. Construction crews will then remove the deck on the south side of the bridge, add additional piers and girders, and finally a new deck.12/12/23 Update:The Dartmouth Bridge will be closed until at least the evening of Thursday the 14 (weather permitting) in order to change traffic configurations to the final phase of construction on the bridge.
12/6/23 Update:
The Dartmouth Bridge will be closed in both directions for five days (weather permitting) beginning Thursday, December 7. Crews will be pouring the middle portion of the deck, and the deck needs at least five days with no traffic on the adjacent lanes to cure properly.12/5/23 Update:
Westbound Dartmouth Avenue across the bridge will be closed tomorrow, Wednesday, December 6 to do a survey before the next bridge pour. The contractor is currently replacing the median on the east side of the bridge, which will be finished around December 15.11/17/23 Update:
Westbound Dartmouth Avenue across the bridge will be closed Saturday, November 18, in order to finish work on the utility hanger on the north side of the bridge before Thanksgiving break.11/16/23 Update:
Westbound Dartmouth Avenue across the bridge will be closed until Friday, November 17 and next Monday, November 20 through Wednesday, November 22 while crews install final pieces of the utility hanger to the north side of the bridge.8/30/23 Update:The Dartmouth Avenue Bridge will be closed on Friday, September 1 and Tuesday, September 5. The bridge will be reopened at the end of each day. The contractor will be pouring the bridge barrier and space on the bridge is needed for equipment to prepare for the pour on Friday and execute the pour on Tuesday.8/18/23 Update:The Dartmouth Bridge closure has been delayed. The bridge will now be closed from Wednesday, August 23 to Sunday, August 27. The contractor will be pouring new concrete on the north half of the deck. Traffic on the bridge vibrates the deck such that the concrete would not cure properly, so the bridge will be closed during the bridge deck pour, and for enough time to allow the concrete to cure properly.
10/17/23 Update:
Dartmouth Avenue will be closed in both directions for construction of the bridge on Thursday, October 19 through midday Friday, October 20. New traffic patterns will be installed, and traffic will continue Friday afternoon using the northernmost lane for westbound traffic and the southernmost lane for eastbound traffic. This traffic pattern will be utilized throughout the weekend.On Monday, October 23, the westbound lane of traffic will be closed during the week for up to three weeks while crews install a utility bridge on the north side of Dartmouth Bridge. Demolition and construction will commence on the middle portion of the bridge while the utility bridge is being installed.