The basketball court at Bates Logan Park is scheduled for reconstruction later this fall due to surface issues identified during testing.
After the new basketball court was completed, the surface did not meet required durability standards, failing pressure tests and showing cracking from underneath. To ensure long-term durability and safety, the court will need to be redone. The reconstruction will not incur any additional costs to the city.
The court is safe to use in the meantime and will remain open for play until reconstruction begins. The replacement work is planned for later this fall and is expected to require a closure of approximately two to four weeks. All other park amenities are expected to remain open and accessible throughout the construction period.
While this may be disappointing, the goal is to deliver a high-quality court that will last for years to come.
For updates on the project timeline and closures, please check this page regularly.
Share Grand Re-opening June 14 on Facebook
Share Grand Re-opening June 14 on Linkedin
Email Grand Re-opening June 14 link
The grand re-opening of Bates Logan Park is Saturday, June 14 from 10 a.m. – noon. Come test out the new playground, race around the bike track, play bocce ball and basketball and see what this new park has to offer!
-
Ribbon cutting and remarks at 10:30 a.m.
-
Food trucks
-
Live DJ
-
Yard games
Share Park Progress - 5.1.25 on Facebook
Share Park Progress - 5.1.25 on Linkedin
Email Park Progress - 5.1.25 link
Progress Update for Bates Logan Park!
- Pump track and bike skills course are being poured
- Bocce ball court has been completed
- New boulder flower bed has been installed
- Irrigation has been completed
- Trees will be selected next week and planted soon afterwards
- The park is track to re-open this summer!
Share Project Progress - 3.14.25 on Facebook
Share Project Progress - 3.14.25 on Linkedin
Email Project Progress - 3.14.25 link
Progress Update for Bates Logan Park!
Share Phase 3 Started on Facebook
Share Phase 3 Started on Linkedin
Email Phase 3 Started link
Phase 3 of Bates Logan Park renovations are underway! Phase 3 construction will run in tandem with the final stages of Phase 2.
Phase 3 Includes:
- Upgraded Irrigation System for the Soccer Field
- Two Bike Skills Parks
- Pump Track
- Bocce Ball Court
- 12 new trees
Share Project Progress - 2.20.25 on Facebook
Share Project Progress - 2.20.25 on Linkedin
Email Project Progress - 2.20.25 link
Progress Update for Bates Logan Park!
- New walking paths have started to be poured, and the remainder is set to be poured by next week.
- The new block staircase has been installed
- The soccer field is currently closed for irrigation system upgrades
Share Project Progress - 11.19.24 on Facebook
Share Project Progress - 11.19.24 on Linkedin
Email Project Progress - 11.19.24 link
Progress Update for Bates Logan Park!
- Work on the playground at Bates Logan has resumed after the snowstorms. All play structures have been installed and look great! The installer is currently finishing up drain work and cosmetic tasks.
- The basketball court is on track to be formed and poured the first week of December, weather permitting.
Share Playground Installation on Facebook
Share Playground Installation on Linkedin
Email Playground Installation link
Phase two is underway with the layout for the new playground complete along with drilling for the equipment. Playground equipment has arrived, and installation is in progress The playground will feature many upgrades for play including an ADA-swing and merry-go-round for wheelchairs.
Share Dirt Work In Full Swing on Facebook
Share Dirt Work In Full Swing on Linkedin
Email Dirt Work In Full Swing link
Phase 2 of Bates Logan Park renovations are in full swing!
Dirt work is ongoing for the basketball court, and the final grade will be established this week.
Major dirt work has begun on the slope, which includes ramp, boulder prep, footers and more!
Share Phase 3 Funding Update on Facebook
Share Phase 3 Funding Update on Linkedin
Email Phase 3 Funding Update link
The Englewood Parks, Recreation, Library and Golf Department has been awarded a $600,000 grant from the Arapahoe County Open Spaces Fund for Phase 3 of Bates Logan Park renovations! 👏