Practice Putting Green Sprinkler with poor distribution uniformity.
previous next
Practice Putting Green Sprinkler with poor distribution uniformity.
Existing West Pump Station
Practice Putting Green Sprinkler with poor distribution uniformity.
Hole #6 Catch Basin Rebuild - Before
Hole #6 Catch Basin Rebuild - In Process
Hole #6 Catch Basin Rebuild – Completed
Hole #1 Catch Basin Rebuild – Before
Hole #1 Catch Basin Rebuild – Completed
Hole #4 Concrete Cart Path Repair
Hole #9 New Asphalt Cart Path
Hole #12 New Asphalt Cart Path - Completed May 16, 2025
Hole #16 New Asphalt Cart Path - Completed May 2, 2025
Hole #17 Green Tee Box – Completed mid-June 2025
Hole #17, Red and Black Tee Box, has been expanded, leveled, and sodded, with a 1500-square-foot tee-able area.
Hole #17 Green Tee Box – Completed mid-June 2025
Hole #17 Green Tee Box—expanded, leveled, and sodded. There is now 1,200 square feet of tee-able area.
Bunker Rebuild – Hole #17
Tree Planted on a Hill
Hole #14 Pond – Fall 2024
Hole #14 Pond – Spring 2025
Husquvarna Robotic Mower
Turflogic Hole #6 on June 5, 2025
Turflogic Hole #6 on September 11, 2025
Turflogic Hole #13 on June 5, 2025
Turflogic Hole #13 on September 11, 2025