Old Hampden Utility Improvements

Share Old Hampden Utility Improvements on Facebook Share Old Hampden Utility Improvements on Twitter Share Old Hampden Utility Improvements on Linkedin Email Old Hampden Utility Improvements link



Project Overview

Old Hampden needs some love, both above and below ground. This street and its aging underground water and stormwater pipelines run directly through the Wellness District of Downtown Englewood serving Craig Hospital, Swedish Medical Center, nearby businesses and residents, office workers, and visitors with its assortment of retail stores and restaurants. Upgrading old infrastructure and enhancing public safety, accessibility and options for getting around the Old Hampden area are key priorities for the City of Englewood and the Englewood Downtown Development Authority.

The Old Hampden Utility Improvements project will begin to address these priorities by replacing aging utility infrastructure and planning for future streetscape improvements to better accommodate all modes of travel through the corridor.

After the Old Hampden Utility Improvement project is completed, the next phase of streetscape improvements will begin in Summer 2025 and continue into Summer 2026. Learn more about Old Hampden Complete Streets here.

Image of CCTV footage of stormwater pipe full of debris.

Aftermath of a water main break on Hampden and Washington.

Infrastructure Improvements

Many of Englewood’s water and stormwater pipes were built in the 1950s. They are nearing the end of their useful life and need to be upgraded or replaced. Water main breaks and stormwater-related flooding have both occurred as a result of aging and undersized infrastructure.

Because of these issues, the replacement of aging infrastructure along Old Hampden has been identified as a top priority for the City of Englewood through its master planning process. In 2020, the City of Englewood developed Master Plans for each of the three utilities which identified the following priorities:

  • Stormwater Master Plan
    • Replacement of stormwater pipelines along Old Hampden and the possible addition of a new, enlarged storm sewer outlet to Little Dry Creek was identified as one of the top three critical infrastructure improvements.
  • Water System Master Plan
    • The Clarkson and Hampden Booster Pump Station and Old Hampden water main were identified as being in need of rehabilitation and replacement.

To help reduce the cost of these critical infrastructure projects and limit construction-related disruptions, the Public Works and Utilities Departments have partnered to make these improvements to the stormwater and water lines at the same time.

Streetscape Improvements

Streetscape improvements and utility improvements have been separated into two projects. Please view Old Hampden Complete Streets Project page to view the project details for streetscape improvements.

The underground pipeline improvements will pave the way for a redesign above ground following Complete Streets design principles.

Green infrastructure (GI) along Brighton Boulevard in Five Points. This GI captures excess stormwater while also providing seating for pedestrians and other street users. (Kevin J. Beaty/Denverite)

Example of proposed streetscape design

Community Input

A key piece of this project is public input. An e-survey on this page in 2022 resulted in public comments that have directly informed preliminary plans. A stakeholder advisory committee, comprised of corridor residents, businesses, hospitals, neighbors, people with disabilities and advocates for safety, sustainability and accessibility has also provided input.

You can view their meeting presentations under “Documents” on this page. To stay informed on the latest project information, subscribe to the project email list at the top of this page.

Stakeholders meeting in the project area. Stakeholders meeting in the project area.


Project Scope

Stormwater Improvements

  • Design improvements for 2,300 feet of stormwater pipeline, inlets and manholes on Old Hampden Avenue between S. Clarkson Street and Lincoln Street
  • Design improvements for 400 feet of stormwater pipeline on Lincoln Street south of Old Hampden Avenue to the outfall on Little Dry Creek
  • Construction of improvements to occur in 2024-2025.

Project Funding

A variety of funding sources will be necessary to complete the design and construction of all aspects of this project, including federal, state, and local sources. Design costs are being funded by Water and Stormwater Funds along with funds from the city’s Public Improvement Fund for the preliminary design of the Complete Streets concept.

Project Schedule

The Old Hampden Complete Streets Project is scheduled to begin in January 2025 and continue through Summer 2025.




Project Overview

Old Hampden needs some love, both above and below ground. This street and its aging underground water and stormwater pipelines run directly through the Wellness District of Downtown Englewood serving Craig Hospital, Swedish Medical Center, nearby businesses and residents, office workers, and visitors with its assortment of retail stores and restaurants. Upgrading old infrastructure and enhancing public safety, accessibility and options for getting around the Old Hampden area are key priorities for the City of Englewood and the Englewood Downtown Development Authority.

The Old Hampden Utility Improvements project will begin to address these priorities by replacing aging utility infrastructure and planning for future streetscape improvements to better accommodate all modes of travel through the corridor.

After the Old Hampden Utility Improvement project is completed, the next phase of streetscape improvements will begin in Summer 2025 and continue into Summer 2026. Learn more about Old Hampden Complete Streets here.

Image of CCTV footage of stormwater pipe full of debris.

Aftermath of a water main break on Hampden and Washington.

Infrastructure Improvements

Many of Englewood’s water and stormwater pipes were built in the 1950s. They are nearing the end of their useful life and need to be upgraded or replaced. Water main breaks and stormwater-related flooding have both occurred as a result of aging and undersized infrastructure.

Because of these issues, the replacement of aging infrastructure along Old Hampden has been identified as a top priority for the City of Englewood through its master planning process. In 2020, the City of Englewood developed Master Plans for each of the three utilities which identified the following priorities:

  • Stormwater Master Plan
    • Replacement of stormwater pipelines along Old Hampden and the possible addition of a new, enlarged storm sewer outlet to Little Dry Creek was identified as one of the top three critical infrastructure improvements.
  • Water System Master Plan
    • The Clarkson and Hampden Booster Pump Station and Old Hampden water main were identified as being in need of rehabilitation and replacement.

To help reduce the cost of these critical infrastructure projects and limit construction-related disruptions, the Public Works and Utilities Departments have partnered to make these improvements to the stormwater and water lines at the same time.

Streetscape Improvements

Streetscape improvements and utility improvements have been separated into two projects. Please view Old Hampden Complete Streets Project page to view the project details for streetscape improvements.

The underground pipeline improvements will pave the way for a redesign above ground following Complete Streets design principles.

Green infrastructure (GI) along Brighton Boulevard in Five Points. This GI captures excess stormwater while also providing seating for pedestrians and other street users. (Kevin J. Beaty/Denverite)

Example of proposed streetscape design

Community Input

A key piece of this project is public input. An e-survey on this page in 2022 resulted in public comments that have directly informed preliminary plans. A stakeholder advisory committee, comprised of corridor residents, businesses, hospitals, neighbors, people with disabilities and advocates for safety, sustainability and accessibility has also provided input.

You can view their meeting presentations under “Documents” on this page. To stay informed on the latest project information, subscribe to the project email list at the top of this page.

Stakeholders meeting in the project area. Stakeholders meeting in the project area.


Project Scope

Stormwater Improvements

  • Design improvements for 2,300 feet of stormwater pipeline, inlets and manholes on Old Hampden Avenue between S. Clarkson Street and Lincoln Street
  • Design improvements for 400 feet of stormwater pipeline on Lincoln Street south of Old Hampden Avenue to the outfall on Little Dry Creek
  • Construction of improvements to occur in 2024-2025.

Project Funding

A variety of funding sources will be necessary to complete the design and construction of all aspects of this project, including federal, state, and local sources. Design costs are being funded by Water and Stormwater Funds along with funds from the city’s Public Improvement Fund for the preliminary design of the Complete Streets concept.

Project Schedule

The Old Hampden Complete Streets Project is scheduled to begin in January 2025 and continue through Summer 2025.


  • Detour Route Update – March 2025

    Share Detour Route Update – March 2025 on Facebook Share Detour Route Update – March 2025 on Twitter Share Detour Route Update – March 2025 on Linkedin Email Detour Route Update – March 2025 link
    supporting image

    The Old Hampden Improvements Project is advancing, and traffic patterns have been updated to accommodate ongoing work in the area.

    The intersection of Logan Street and Old Hampden Avenue will fully close again on Monday, March 3 as construction progresses. The closure on E. Hampden Avenue from S. Grant Street to S. Pennsylvania Street is estimated to last until early May.

    These closures are essential for upgrading aging infrastructure and preparing the area for streetscape improvements aimed at enhancing public safety and accessibility.

  • Detour Route Update - February 2025

    Share Detour Route Update - February 2025 on Facebook Share Detour Route Update - February 2025 on Twitter Share Detour Route Update - February 2025 on Linkedin Email Detour Route Update - February 2025 link
    supporting image

    The Old Hampden Improvements Project is progressing, and traffic patterns have been updated. Logan Street has reopened temporarily at Old Hampden, improving traffic flow while work continues in the area.

    What to Expect:

    • Street closures will continue in phases along Old Hampden Avenue—please follow updated detour signs and allow extra travel time.

    • Logan Street at Old Hampden is expected to fully close again in March as construction advances.

    These closures are essential for upgrading aging infrastructure and preparing the area for streetscape improvements aimed at enhancing public safety and accessibility.

  • Bert Shuttle Route Update

    Share Bert Shuttle Route Update on Facebook Share Bert Shuttle Route Update on Twitter Share Bert Shuttle Route Update on Linkedin Email Bert Shuttle Route Update link
    supporting image

    Due to construction along Old Hampden Avenue, Englewood’s free shuttle service through the Wellness District has been rerouted.

    Stop 8 has been temporarily rerouted to the northwest corner of Sherman Street and Old Hampden Avenue. Stop 13 has been temporarily rerouted to the southwest corner of Pennsylvania Street and Old Hampden Avenue.

    Learn more about Englewood’s FREE bert shuttle at englewoodco.gov/bert

  • Construction Begins for Old Hampden Improvements

    Share Construction Begins for Old Hampden Improvements on Facebook Share Construction Begins for Old Hampden Improvements on Twitter Share Construction Begins for Old Hampden Improvements on Linkedin Email Construction Begins for Old Hampden Improvements link
    supporting image

    The City of Englewood is excited to announce the official start of the improvements on Old Hampden in the Wellness District.

    Starting Monday, January 6, 2025, crews will begin critical utility upgrades along Old Hampden Avenue, kicking off a two-phase project that will enhance the infrastructure and streetscape of this important corridor.

    The first road closure will impact E. Hampden Avenue between S. Pennsylvania Street and S. Grant Street. This section of road will be closed to through traffic as crews begin the utility work. Detours will be in place to help guide drivers around the closure. Please follow posted detour signs and allow extra time for your commute as work progresses. This closure is expected to last until late February. Afterward, rolling closures will continue along Old Hampden Avenue, moving toward S. Broadway. The sidewalk on the south side of Old Hampden will remain open for pedestrians throughout construction.

    This closure marks the start of Phase 1, which will focus on upgrading underground water, sewer, and stormwater systems to ensure reliable service for the future. Phase 1 is expected to continue through Summer 2025.

    What’s Next?

    The Old Hampden Complete Streets Project will be completed in two phases:

    • Phase 1 (January–Summer 2025): Underground utility upgrades, including the replacement of aging water, sewer and stormwater systems.
    • Phase 2 (Summer 2025–Summer 2026): Above-ground streetscape improvements, including ADA-compliant sidewalks, upgraded bus stops and traffic-calming measures. Learn more about the streetscape improvements here.

    Subscribe to this page for the most up-to-date project information and street closure information. Thank you for your patience as we work to improve Old Hampden Avenue and create a safer, more accessible corridor for all who live, work, and visit Englewood.

  • Project Start Date

    Share Project Start Date on Facebook Share Project Start Date on Twitter Share Project Start Date on Linkedin Email Project Start Date link

    The Old Hampden Complete Streets Project is scheduled to begin on January 6, 2025. City staff and the contractor are currently preparing a detailed block-by-block schedule to outline when road closures and detours will occur for each phase of the project.

    To stay informed about road closures, detours and project updates, we encourage you to subscribe to this page for the latest information throughout the project.

    Thank you for your patience as we work to enhance the streetscape and infrastructure on Old Hampden.

  • October Update

    Share October Update on Facebook Share October Update on Twitter Share October Update on Linkedin Email October Update link

    Timber Wolf Excavating has been selected as the contractor and is in the contract approval process, work will be started in late 2024.

  • August Update

    Share August Update on Facebook Share August Update on Twitter Share August Update on Linkedin Email August Update link

    The Utilities project has been broken into three projects. The sanitary pipe will be lined independently of the main project and the pump station was also separated into its own project to ensure the work is completed by a contractor with the appropriate expertise.

    Remaining in the Old Hampden Utilities project is the replacement of the storm and water lines along the corridor as well as lining of the storm pipe on Lincoln.

    This project is wrapping up the final stages of design and plans on going out to bid around the new year.

Page last updated: 21 Mar 2025, 10:16 AM