Update - May 2026

Concrete placement was completed for the westbound lane from Santa Fe to the Frontage Road. The bottom two lifts of asphalt for the westbound lane have been placed from the Frontage Road to the bridge over the South Platte River.
Following adequate curing of the concrete, the top lift of asphalt over the entire project is planned the week following Memorial Day.
Estimated completion of the project is early June, 2026.