April 25, 2026 Update
Concrete and Asphalt Pavement replacement has been completed in the eastbound lane from Santa Fe west to the bridge. Traffic control will be shifting traffic flow on Friday, April 24.
While the City Utilities project continues west of the bridge, that traffic flow will remain on the north side of Union and traffic will be shifted west of the bridge to to the south side of Union to Santa Fe to allow reconstruction to begin on the westbound lane. Click the links below to view the traffic control plans:
- Phase 1 Traffic Control Plan (Mid March to Mid/Late April)
- Phase 2 Traffic Control Plan (Mid/Late April to Late May)
The project is on schedule with anticipated completion early summer.