7.1.21 Project Update

US-285 & S. Broadway Users,

This email is the sixth in a series of monthly updates regarding the US-285 & S. Broadway Interchange Reconstruction Project.

In the last month, the project team determined the most suitable bridge structure design based on the characteristics of the interchange and relative cost of the available structure types. The final structure will be a two-span bridge using precast concrete tub-girders. The team also refined the roadway geometry and established preliminary limits of reconstruction. The team developed preliminary grading plans and drainage plans. The team continues working with city staff to narrow down aesthetic concepts for the interchange.

In the coming month, the team will be submitting a preliminary design package to the city and CDOT for review.

Best,
Englewood Public Works

Preliminary Design; may not reflect Final Design

Preliminary Design; may not reflect Final Design

Share 7.1.21 Project Update on Facebook Share 7.1.21 Project Update on Twitter Share 7.1.21 Project Update on Linkedin Email 7.1.21 Project Update link
#<Object:0x00007f80483b6440>