4.1.22 Update

US-285 & S. Broadway Users,

This is the fifteenth in a series of monthly updates regarding the US-285 & S. Broadway Interchange Reconstruction Project.

In the last month, city staff worked with CDOT to develop a draft amendment to the intergovernmental agreement for the project which, upon execution, will allocate additional state and federal funds to the project. CDOT has continued reviewing the plans and has granted the Utilities clearance for the project. The design team is expecting to receive the remaining CDOT clearances for the Environmental and Right-of-Way reviews within the next month.

Upon receiving the remaining clearances from CDOT, the project will go to FHWA for approval, then be advertised for construction.

Best,

Englewood Public Works