3.1.22 Update
US-285 & S. Broadway Users,
This is the fourteenth in a series of monthly updates regarding the US-285 & S. Broadway Interchange Reconstruction Project.
In the last month, the consultant team continued addressing comments from the city and CDOT on the drainage, water quality, traffic signal plans, utility plans, and more. The consultant finalized the design and submitted the final bid package for approval from the city, CDOT, and FHWA.
In the next month, the city will seek final clearances and approval to advertise for construction from CDOT and FHWA.
Best,
Englewood Public Works