October 2026 Update

Construction continues along the South Broadway corridor as crews work toward completing the South Broadway Complete Streets project. October's work included improvements to sidewalks, medians and bus stops, along with progress on Oxford Avenue improvements. In November, crews will focus on completing remaining infrastructure work, installing landscaping and site furnishings, and finishing final restoration activities. Below is a look at work completed in October and what to expect in November.

Work Completed in October

  • Oxford Avenue Improvements: Crews completed excavation and placement of base material, followed by curb and gutter forming, drainage work, concrete placement and corner improvements.
  • Bus Stop Improvements: New bus shelters, trash bins and benches were installed at Chenango, Tufts, Quincy, Mansfield and Kenyon avenues.
  • Pavement Markings: New pavement markings were installed around Chenango, Tufts, Mansfield and Kenyon avenues.
  • Planter Boxes: Topsoil was placed in the new planter boxes at Quincy, Mansfield and Kenyon avenues.
  • Sidewalk and Light Pole Improvements: Sidewalk improvements and light pole work were completed along the west side of South Broadway.
  • Median Improvements: Crews completed median work and installed median cover at Mansfield, Chenango, Quincy and Kenyon avenues.

Work Anticipated in November

Construction will continue throughout the South Broadway corridor in November, focusing on completing improvements at Oxford Avenue, installing landscaping and site furnishings, and finishing restoration work. Construction will pause for the Thanksgiving holiday.

  • Oxford Avenue Improvements: Crews will install storm drainage piping, followed by concrete placement and asphalt paving. These activities are expected to be completed in early November.
  • Bus Stops and Site Furnishings: Following a walkthrough with the city to confirm placement, crews will install benches and other site furnishings throughout the corridor.
  • Pavement Markings: Crews will complete the remaining pavement striping and markings throughout the project corridor.
  • Landscaping and Irrigation: Crews will install irrigation systems and plant trees and shrubs.
  • Final Inspections and Restoration: Crews will conduct internal inspections, address remaining punch-list items, and continue site cleanup and restoration of disturbed areas.

Work activities and schedules may change based on weather, site conditions and construction progress.

Share October 2026 Update on Facebook Share October 2026 Update on X (formerly Twitter) Share October 2026 Update on Linkedin Email October 2026 Update link