Progress continues on the Oxford Pedestrian Bridge, and the bridge is expected to open in early May. Here’s the latest progress:
- Installation of the ADA railings is expected to be completed by mid-month
- Bridge supports and piers were recently stained
- The green Englewood logos have been painted
- Oxford Avenue will be restriped
- Sprinkler irrigation repairs are underway
- Power meter installation for the bridge lights
- Dog park reconstruction
- Resodding and reseeding nearby areas