This is the third in a series of monthly updates regarding the Oxford Ave Pedestrian Bridge Project.
In the last month, the project team finalized the structure selection report and determined the preferred structure type and configuration for the bridge. The team refined the plan and profile for the approach paths, determined where structural and landscaping retaining walls would be required, and developed preliminary plans & specifications for review by the City and CDOT.
The City hosted a virtual public information meeting for the project on April 22, 2021. A recording of this meeting can be found on the project webpage: https://www.engaged.englewoodco.gov/oxford-ave