South Englewood Flood Reduction Project

Share South Englewood Flood Reduction Project on Facebook Share South Englewood Flood Reduction Project on Twitter Share South Englewood Flood Reduction Project on Linkedin Email South Englewood Flood Reduction Project link

The South Englewood Flood Reduction Project will reduce flooding in the South Englewood drainage basin by constructing new stormwater detention ponds and making stormwater pipe improvements. The stormwater detention ponds will be located along the west side of South Navajo Street, just south of West Radcliff Avenue. Pipe improvements will be made in the Rotolo Park, Stanford Avenue, South Navajo Street, and Oxford Avenue areas.

This project is estimated to cost $23 million and is funded by stormwater fees.


Construction Outreach

A notification was sent via mail to residents in certain effected areas in December 2023. Businesses impacted by construction along Navajo will be contacted by the contractor.

Construction Schedule

Construction bids were received in September 2023 with American Civil Constructors being the low bidder.

Groundbreaking for this project is scheduled for Thursday, February 22 at 3 p.m. at the southwest corner of the intersection of Radcliff Ave. and Navajo St.

The majority of major construction efforts are scheduled to be completed in Winter 2025. Some final work, such as landscaping, will take place in Spring 2025.

Construction Impacts

  • Sections of Quincy Street, Navajo Street and Stanford Avenue near Navajo Street will need to be closed during construction. Detours will be put in place to route traffic around the closures.
    • Navajo St. between Oxford and Quincy is open to two-way traffic as of May 9, 2024.
    • Navajo St. south of Quincy will be closed and detoured until further notice as work continues on the new stormwater detention ponds.
  • Traffic control and partial lane closures will be in place on Oxford Avenue, Navajo Street and Stanford Avenue. Traffic can travel through these streets most of the time, but there may be delays.
  • Heavy equipment being used will create construction noise. Construction hours will be limited to Monday through Friday, 7 a.m. – 7 p.m. Limited night and weekend work may be needed under special circumstances.
  • Materials, equipment, and debris will need to be delivered to and removed from the construction area.
  • Rotolo Park will be closed for pipe installation and earthwork.
  • Roadways impacted by construction will be restored and repaved at the end of the project. Temporary paving may be in place for a period of time before final paving takes place.

Project Elements

Stormwater Detention Ponds

The South Englewood Flood Reduction Project will construct detention ponds to reduce flooding. During rain events, the stormwater detention ponds will fill with water providing storage for runoff. When the rain stops, the stormwater detention pond is designed to drain within 24 to 48 hours following rain or snowmelt events.

The larger pond will be open for recreation or passive open space after it drains.

Learn more about how a stormwater detention pond works.

Construction of the stormwater detention ponds will require demolishing existing buildings on property acquired by the city in April 2022. After demolition, many yards of dirt will be removed from the site to create storage for stormwater runoff.

New Pipe: Tunneling

To minimize impacts on residents, sections of new stormwater pipe will be installed by a machine that tunnels below the surface. This tunnel boring machine will install storm sewer pipe on Stanford Drive and Stanford Avenue west of Rotolo Park. Certain sections of road will be excavated to create boring pits, which will then be used to insert and remove the boring machine and install the new stormwater pipe. This tunneling work will allow residents to continue using Stanford Drive and Stanford Avenue near Rotolo Park during construction.

New Pipe: Open Cut Construction

A new stormwater pipe will be installed by open-cut trench excavation at several locations throughout the project site, including Rotolo Park, along Stanford Avenue east of Navajo Street, and along Navajo Street between Stanford Avenue and Quincy Avenue. Installing these pipes will require full and partial road closures and detours. This type of pipe installation is more cost effective than tunneling but impacts traffic more.

Existing Pipe: Rehabilitation

To carry more stormwater and to ensure reliable service, this project will also rehabilitate and or repair the existing stormwater pipe on Oxford Avenue from Santa Fe to the South Platte River west of Santa Fe Drive. Most of the repairs will be completed below ground by accessing the pipe from manholes at the surface. Short segments of pipe on Oxford Avenue west of Santa Fe Drive will require digging to repair. Traffic control will be needed at repair sites, but no full road closures are planned for this work.

Earth Work: Rotolo Park

A section of Rotolo Park will be regraded by moving dirt to direct stormwater runoff into the new stormwater pipes and stormwater detention ponds. This work will close a section of Rotolo Park for a period of time and disturb areas with existing grass. Any grass and landscaping impacted by this work will be restored after construction is complete.


*Pipe capacity needs based on a 25-year storm event of 1.66 inches of rain in one hour. CFS stands for cubic feet per second and is a measurement for flow. 1 CFS is equal to 7.5 gallons flowing past a particular point in one second.

A Cost-Effective Solution

The South Englewood Flood Reduction Project will enhance the city’s storm sewer system, allowing more stormwater to flow through the system from upstream locations, including areas near Acoma Street south of Tufts Avenue and Rotolo Park.

The City of Englewood realized addressing the challenge of localized flooding would be costly. The city contracted with engineering experts to identify and prioritize the most effective flood reduction projects and how to invest city resources wisely.



Frequently Asked Questions

What is a stormwater detention pond?

Answer: A stormwater detention pond holds stormwater during major rain events, delaying the time that water reaches the existing stormwater system, which allows the existing system to carry more stormwater over a greater length of time.

Why is this work taking place in an area not as prone to flooding like the Acoma Street Area near Tufts Ave?

Answer: New stormwater pipes and drains are being installed in the Acoma Street area as part of a separate project. The South Englewood Flood Reduction Project is critical because it removes a bottle neck in the system downstream from flood prone areas in the upper South Englewood Drainage Basin. Without removing this bottleneck, additional drains and new pipes would not be as effective upstream because that water would still be restricted downstream.

Why wasn’t this work completed sooner?

Answer: Large infrastructure improvements are costly and involve a significant amount of study and design work. Englewood first strategically invested in engineering studies to identify and prioritize the most important projects. Next, funding had to be secured through increased stormwater fees as well as a stormwater bond issuance to be able to fund this project and others. Finally, it takes time to design large infrastructure projects to ensure that they work successfully for years to come.

Will this project address all street flooding issues?

Answer: No. The South Englewood Flood Reduction Project, along with other South Englewood Drainage Basin stormwater projects, are being designed to manage flows from a storm event that has a 4% chance of occurring in any given storm event, also called a 25-year storm. Based on current National Oceanic and Atmospheric Admiration (NOAA) data, a 25-year storm for Englewood has a rainfall depth of 1.66 inches of rain in one hour. Rainfall greater than 1.66 inches in an hour can still potentially create street flooding after this project is complete, but significantly less than it would historically prior to installation of the South Englewood Flood Reduction project and related upstream improvements in the South Englewood Drainage basin. Englewood City Council determined in 2020 that designing for a 25-year storm event was an appropriate balance between flood reduction and overall project cost. Additional surface improvements are being considered to keep higher flows within the public streets and right of way.

I live in the project area; how will I be impacted?

Answer: Residents can expect to see vehicular and pedestrian detours in the project area. Residents can also expect to see an increase in construction related traffic along Navajo Street, Windermere Street, Stanford Ave and Quincy Avenue as well as in the Rotolo Park area.

When will the construction be complete?

The majority of major construction efforts are scheduled to be completed in Winter 2025. Some final work, such as landscaping, will take place in Spring 2025.

The South Englewood Flood Reduction Project will reduce flooding in the South Englewood drainage basin by constructing new stormwater detention ponds and making stormwater pipe improvements. The stormwater detention ponds will be located along the west side of South Navajo Street, just south of West Radcliff Avenue. Pipe improvements will be made in the Rotolo Park, Stanford Avenue, South Navajo Street, and Oxford Avenue areas.

This project is estimated to cost $23 million and is funded by stormwater fees.


Construction Outreach

A notification was sent via mail to residents in certain effected areas in December 2023. Businesses impacted by construction along Navajo will be contacted by the contractor.

Construction Schedule

Construction bids were received in September 2023 with American Civil Constructors being the low bidder.

Groundbreaking for this project is scheduled for Thursday, February 22 at 3 p.m. at the southwest corner of the intersection of Radcliff Ave. and Navajo St.

The majority of major construction efforts are scheduled to be completed in Winter 2025. Some final work, such as landscaping, will take place in Spring 2025.

Construction Impacts

  • Sections of Quincy Street, Navajo Street and Stanford Avenue near Navajo Street will need to be closed during construction. Detours will be put in place to route traffic around the closures.
    • Navajo St. between Oxford and Quincy is open to two-way traffic as of May 9, 2024.
    • Navajo St. south of Quincy will be closed and detoured until further notice as work continues on the new stormwater detention ponds.
  • Traffic control and partial lane closures will be in place on Oxford Avenue, Navajo Street and Stanford Avenue. Traffic can travel through these streets most of the time, but there may be delays.
  • Heavy equipment being used will create construction noise. Construction hours will be limited to Monday through Friday, 7 a.m. – 7 p.m. Limited night and weekend work may be needed under special circumstances.
  • Materials, equipment, and debris will need to be delivered to and removed from the construction area.
  • Rotolo Park will be closed for pipe installation and earthwork.
  • Roadways impacted by construction will be restored and repaved at the end of the project. Temporary paving may be in place for a period of time before final paving takes place.

Project Elements

Stormwater Detention Ponds

The South Englewood Flood Reduction Project will construct detention ponds to reduce flooding. During rain events, the stormwater detention ponds will fill with water providing storage for runoff. When the rain stops, the stormwater detention pond is designed to drain within 24 to 48 hours following rain or snowmelt events.

The larger pond will be open for recreation or passive open space after it drains.

Learn more about how a stormwater detention pond works.

Construction of the stormwater detention ponds will require demolishing existing buildings on property acquired by the city in April 2022. After demolition, many yards of dirt will be removed from the site to create storage for stormwater runoff.

New Pipe: Tunneling

To minimize impacts on residents, sections of new stormwater pipe will be installed by a machine that tunnels below the surface. This tunnel boring machine will install storm sewer pipe on Stanford Drive and Stanford Avenue west of Rotolo Park. Certain sections of road will be excavated to create boring pits, which will then be used to insert and remove the boring machine and install the new stormwater pipe. This tunneling work will allow residents to continue using Stanford Drive and Stanford Avenue near Rotolo Park during construction.

New Pipe: Open Cut Construction

A new stormwater pipe will be installed by open-cut trench excavation at several locations throughout the project site, including Rotolo Park, along Stanford Avenue east of Navajo Street, and along Navajo Street between Stanford Avenue and Quincy Avenue. Installing these pipes will require full and partial road closures and detours. This type of pipe installation is more cost effective than tunneling but impacts traffic more.

Existing Pipe: Rehabilitation

To carry more stormwater and to ensure reliable service, this project will also rehabilitate and or repair the existing stormwater pipe on Oxford Avenue from Santa Fe to the South Platte River west of Santa Fe Drive. Most of the repairs will be completed below ground by accessing the pipe from manholes at the surface. Short segments of pipe on Oxford Avenue west of Santa Fe Drive will require digging to repair. Traffic control will be needed at repair sites, but no full road closures are planned for this work.

Earth Work: Rotolo Park

A section of Rotolo Park will be regraded by moving dirt to direct stormwater runoff into the new stormwater pipes and stormwater detention ponds. This work will close a section of Rotolo Park for a period of time and disturb areas with existing grass. Any grass and landscaping impacted by this work will be restored after construction is complete.


*Pipe capacity needs based on a 25-year storm event of 1.66 inches of rain in one hour. CFS stands for cubic feet per second and is a measurement for flow. 1 CFS is equal to 7.5 gallons flowing past a particular point in one second.

A Cost-Effective Solution

The South Englewood Flood Reduction Project will enhance the city’s storm sewer system, allowing more stormwater to flow through the system from upstream locations, including areas near Acoma Street south of Tufts Avenue and Rotolo Park.

The City of Englewood realized addressing the challenge of localized flooding would be costly. The city contracted with engineering experts to identify and prioritize the most effective flood reduction projects and how to invest city resources wisely.



Frequently Asked Questions

What is a stormwater detention pond?

Answer: A stormwater detention pond holds stormwater during major rain events, delaying the time that water reaches the existing stormwater system, which allows the existing system to carry more stormwater over a greater length of time.

Why is this work taking place in an area not as prone to flooding like the Acoma Street Area near Tufts Ave?

Answer: New stormwater pipes and drains are being installed in the Acoma Street area as part of a separate project. The South Englewood Flood Reduction Project is critical because it removes a bottle neck in the system downstream from flood prone areas in the upper South Englewood Drainage Basin. Without removing this bottleneck, additional drains and new pipes would not be as effective upstream because that water would still be restricted downstream.

Why wasn’t this work completed sooner?

Answer: Large infrastructure improvements are costly and involve a significant amount of study and design work. Englewood first strategically invested in engineering studies to identify and prioritize the most important projects. Next, funding had to be secured through increased stormwater fees as well as a stormwater bond issuance to be able to fund this project and others. Finally, it takes time to design large infrastructure projects to ensure that they work successfully for years to come.

Will this project address all street flooding issues?

Answer: No. The South Englewood Flood Reduction Project, along with other South Englewood Drainage Basin stormwater projects, are being designed to manage flows from a storm event that has a 4% chance of occurring in any given storm event, also called a 25-year storm. Based on current National Oceanic and Atmospheric Admiration (NOAA) data, a 25-year storm for Englewood has a rainfall depth of 1.66 inches of rain in one hour. Rainfall greater than 1.66 inches in an hour can still potentially create street flooding after this project is complete, but significantly less than it would historically prior to installation of the South Englewood Flood Reduction project and related upstream improvements in the South Englewood Drainage basin. Englewood City Council determined in 2020 that designing for a 25-year storm event was an appropriate balance between flood reduction and overall project cost. Additional surface improvements are being considered to keep higher flows within the public streets and right of way.

I live in the project area; how will I be impacted?

Answer: Residents can expect to see vehicular and pedestrian detours in the project area. Residents can also expect to see an increase in construction related traffic along Navajo Street, Windermere Street, Stanford Ave and Quincy Avenue as well as in the Rotolo Park area.

When will the construction be complete?

The majority of major construction efforts are scheduled to be completed in Winter 2025. Some final work, such as landscaping, will take place in Spring 2025.

  • March 2025 Update

    Share March 2025 Update on Facebook Share March 2025 Update on Twitter Share March 2025 Update on Linkedin Email March 2025 Update link
    supporting image

    The South Englewood Flood Reduction Project continues to make significant progress!

    • On March 14, the tunnel boring machine (TBM) successfully completed Run 2 and has now been removed from the site.
    • Crews are installing the permanent pipe for Run 2 and securing it in place with grout.
    • Work on the stormwater ponds is moving forward with gabion baskets, lighting, and concrete installation.

    Several infrastructure projects are happening in South Englewood, including lead service line replacements. Learn more about the Lead Reduction Program here.

    We appreciate your patience as we continue this vital project.

  • South Englewood Flood Reduction Site B Update

    Share South Englewood Flood Reduction Site B Update on Facebook Share South Englewood Flood Reduction Site B Update on Twitter Share South Englewood Flood Reduction Site B Update on Linkedin Email South Englewood Flood Reduction Site B Update link

    Over February, the contractor and construction crew made progress on the new stormwater ponds off Navajo Street and the second tunnel run along Stanford Drive.

    The pond features include stormwater elements such as trickle channels in both ponds, a concrete base at Pond A, and a concrete baffle wall at Pond B. The baffle wall was a significant effort to construct due to its large amount of rebar, which had to be cut, formed, and installed by hand. Non-stormwater features, including gabion baskets and light poles, have also begun to be installed at the ponds.

    At the tunnel, the crew successfully launched the Tunnel Boring Machine (TBM) for Run 2 along Stanford Drive this month and has begun tunneling toward Stanford Avenue, where it will connect with Run 1. Both runs are being constructed using the two-pass method, meaning a temporary tunnel is built behind the TBM, and once the entire run is complete, the permanent pipe is slid and grouted into place. Crews are currently sliding the pipe into place for Run 1 and are more than halfway through this process.

  • South Englewood Flood Reduction Project Update

    Share South Englewood Flood Reduction Project Update on Facebook Share South Englewood Flood Reduction Project Update on Twitter Share South Englewood Flood Reduction Project Update on Linkedin Email South Englewood Flood Reduction Project Update link

    The South Englewood Flood Reduction Project continues to make significant progress, with the Tunnel Boring Machine (TBM) achieving a major milestone. The TBM has successfully completed its first run, boring over 1,440 feet to connect Rotolo Park with new stormwater detention ponds on the west side of South Navajo Street. This crucial tunneling work is a cornerstone of the project, designed to reduce flooding and improve stormwater flows throughout the South Englewood drainage basin.

    The project team, including Englewood Public Works, American Civil Constructors (ACC) and subcontractor Northstar, is utilizing a two-pass tunneling method. The first pass establishes a temporary tunnel, and the second pass installs and grouts the new stormwater pipe into place.

    With the first run complete, the TBM is preparing for the second, shorter section of approximately 230 feet. Breakthrough for this final segment is expected in about six to twelve weeks.

    The project is funded by stormwater fees and is expected to be substantially complete by this spring, including final landscaping.

  • Rotolo Park Tree Removal FAQs

    Share Rotolo Park Tree Removal FAQs on Facebook Share Rotolo Park Tree Removal FAQs on Twitter Share Rotolo Park Tree Removal FAQs on Linkedin Email Rotolo Park Tree Removal FAQs link

    Why are the trees being removed?

    The trees that are being removed were either in conflict with the South Englewood Flood Reduction project’s design or were deemed unhealthy or unsafe by Parks, Recreation, Library and Golf.

    What does it mean to be in conflict with the design?

    The trees that were in conflict with the design were either at an elevation that was changing or in a location that required excavation for the new design. The project’s design includes raising the west bank of the detention facility that comprises the Rotolo field. Raising the west bank is necessary to provide the head pressure needed to force water into the pipe at the new outlet structure while simultaneously providing additional flood protection for residents on Stanford Avenue. The design also includes excavating for a trickle channel on the south side of the park. This will require the installation of a block wall and removal of a portion of the south bank of the Rotolo field.

    How was it determined that a tree was unhealthy or unsafe?

    The City Arborist inspected the trees in the Rotolo field area and found four trees to not be in good health with decay in the tree trunks.

    Why couldn’t the project work around the existing trees?

    The project couldn’t work around the existing trees for a few different reasons. For the trees on the west bank the increase in elevation that is required to increase stormwater capacity would have necessitated burying the trees, which would not have allowed them to survive.

    For the trees on the south bank the new outlet structure and trickle channel require excavation which completely alter the topography of the area. The outlet and trick channel could not have shifted northward without decreasing Rotolo field’s viability as a recreational facility in dry weather conditions and resulted in a negative impact to the sledding hill in the park. Additionally, a northward shift would have increased the complexity of the project due to existing underground utilities.

    How many trees are being removed?

    A total of 14 trees were removed in October 2024. Nine were in conflict with the South Englewood Flood Reduction project, three were unhealthy and removed at PRLG’s request and two were deemed unsafe and unhealthy by a combined PW and PRLG team.

    Was the tree removal part of the Parks Bond that is up for vote this November?

    No. This series of tree removals was part of the South Englewood Flood Reduction project, which is fully funded by Public Works and approved for construction by council in 2023.

    How was this project communicated to the neighborhood?

    This was communicated by a physical mailer that was distributed to 265 residences hand distribution of a door hanger to residences most nearest the disruption. A project employee also had several one-on-one conversations with residents whose properties border the park and were most affected by the tree removal.

    Will the trees be replaced?

    Yes, in 2025 15 new trees will be planted in Rotolo park as well as additional 44 trees planted around the new detention ponds.

    Was the tree removal always part of the South Englewood Flood Reduction project?

    Yes. There were five trees on the south side of Rotolo that were in conflict with the original design. An unforeseen circumstance did lead to a design change after construction kicked off that led to the removal of the trees on the west bank of the pond. Additionally, the City Arborist inspected the trees in the area and determined that some were unhealthy or dead and their removal was included as part of this effort.


  • W Stanford Ave Detour

    Share W Stanford Ave Detour on Facebook Share W Stanford Ave Detour on Twitter Share W Stanford Ave Detour on Linkedin Email W Stanford Ave Detour link

    Starting October 14, W. Stanford Ave. will be closed at W. Stanford Pl. for construction as part of the South Englewood Flood Reduction Project, focusing on stormwater pipe improvements in the Rotolo Park area. Drivers are advised to follow the posted detour routes and heed all traffic signs.

  • Rotolo Park Field Closure

    Share Rotolo Park Field Closure on Facebook Share Rotolo Park Field Closure on Twitter Share Rotolo Park Field Closure on Linkedin Email Rotolo Park Field Closure link
    supporting image

    Effective October 7, 2024, the field at Rotolo Park will be closed through spring as part of the ongoing South Englewood Flood Reduction Project.

    The closure is necessary to complete several key improvements aimed at reducing the risk of flooding in the surrounding area, including:

    • Grading the fields for improved drainage.
    • Installing a trickle channel to manage water flow.
    • Constructing head and wing walls as part of an outlet structure to efficiently direct water flow.
    • Connecting Rotolo Park to the new flood reduction network currently under construction.

    While the fields will remain closed during this work, the playground will remain open for public use.

    We appreciate your patience as we work to make our stormwater infrastructure safer and more resilient. Stay tuned for project updates and completion timelines.

  • 6/27/2024 Detour Update

    Share 6/27/2024 Detour Update on Facebook Share 6/27/2024 Detour Update on Twitter Share 6/27/2024 Detour Update on Linkedin Email 6/27/2024 Detour Update link
    supporting image

    Please review the updated detour map for the South Englewood Flood Reduction Project, which now includes new one-way detours on Navajo St. and Windemere St. These detours will be in place for several months as construction continues on the new detention pond. For your safety and convenience, please follow the posted detour signs.

  • Tunnel Boring Machine Excavation

    Share Tunnel Boring Machine Excavation on Facebook Share Tunnel Boring Machine Excavation on Twitter Share Tunnel Boring Machine Excavation on Linkedin Email Tunnel Boring Machine Excavation link
    supporting image

    The South Englewood Flood Reduction Project is progressing with the use of advanced tunneling technology. The project aims to mitigate flood risks in the area while minimizing disruptions to residents.

    Englewood Public Works is working with American Civil Constructors (ACC) and subcontractor Northstar to employ a Tunnel Boring Machine (TBM) designed to excavate underground to accommodate the new pipe. The tunneling will cover approximately 1,600 feet between the new detention pond and Rotolo Park. The tunnel is constructed using the two pass method, which involves installing sections of the tunnel in 4-5' increments as the TBM makes its first pass through the future tunnel location, followed by pipe sections on its second pass therefore creating the completed tunnel.

    Utilizing the TBM was chosen over traditional open cut excavation methods due to the depth of the project and will reduce the impact to residents along Standford Ave.

    Stay tuned for continued updates as the South Englewood Flood Reduction Project continues construction throughout 2024.

  • Quincy Ave. & Navajo St. Closure Update

    Share Quincy Ave. & Navajo St. Closure Update on Facebook Share Quincy Ave. & Navajo St. Closure Update on Twitter Share Quincy Ave. & Navajo St. Closure Update on Linkedin Email Quincy Ave. & Navajo St. Closure Update link
    supporting image
    The Quincy Avenue and Navajo Street intersection is now open.
    Additionally, Navajo Street between Quincy Avenue and Oxford Avenue is also reopened to two-way traffic. A two-way detour on Windermere Street is again in effect. This detour is expected to remain in place for the remainder of 2024.
    Navajo Street south of Quincy Avenue will remain closed at this time as work on the future detention ponds continues.

    We appreciate everyone's patience during the closure. This milestone represents just one step forward in our comprehensive efforts to mitigate flooding risks and safeguard our community.
  • Road Closure Updates 3/27/24

    Share Road Closure Updates 3/27/24 on Facebook Share Road Closure Updates 3/27/24 on Twitter Share Road Closure Updates 3/27/24 on Linkedin Email Road Closure Updates 3/27/24 link
    supporting image

    As part of the ongoing South Flood Reduction Project, there will be some temporary road closures and detours to keep everyone safe and sound.

    🚦 Navajo St. Detour:

    S. Navajo Street will be closed from Stanford Avenue to Quincy Avenue in both directions.

    For those wanting to travel south towards S. Navajo Street, please follow the detour route below:

    • All traffic will be redirected onto eastbound Oxford Avenue
    • Turn south onto South Broadway towards Belleview Avenue
    • Finally, turn west onto Belleview Avenue to Windemere Street

    Northbound traffic on S. Navajo Street will be detoured onto S. Windermere Street.

    🚦 Westbound Quincy Detour:

    Westbound Quincy Avenue will be detoured onto Jason Street. W. Quincy Avenue will continue to be closed at the Navajo intersection. Eastbound Quincy Avenue will be open to one-way traffic from S. Windemere Street towards S. Navajo Street.

    Navajo St. between Oxford and Quincy is expected to reopen to two-way traffic in early May. Navajo St. south of Quincy will be closed and detoured until further notice as work continues on the new stormwater detention ponds. Pay close attention to detour signs and follow the designated routes.

    The current phase involves sanitary updates as well as storm drain work. This crucial work aims to enhance our community's resilience and safeguard against flooding.

Page last updated: 20 Mar 2025, 12:50 PM