A Better Broken Tee: March 2026 Update
Broken Tee Golf Course is currently undergoing an extensive renovation on Holes 1 through 6 to resolve chronic drainage issues caused by the underlying former landfill. To address this, Verde Sports Construction, the contractor awarded this project, is excavating the topsoil, installing a grid of drain pipes every 15 feet within 12x12 trenches, adding a custom root zone topsoil blend and laying fresh sod over 5 acres.
While the new turf may take a year or two to perfectly match the rest of the course in color and texture, the project is on track for a May reopening. This overhaul will finally ensure healthy, consistent playing conditions across the entire course, allowing golfers to hit off of grass rather than dirt.
Learn more about this update by watching the video below!